claim of Rs.91,013.72. There is a
separate claim made by the claimant under claim No.6
as claim for extra work done. Claim ... items under claim No.6 includes the claim of
Rs.91,013.72 and the claim for extra items of work
can be made only
original tender, the contractor cannot claim any extra rate. He can claim extra rate only if that class of work is not provided ... fact that the grievance of the contractor was to claim extra charges for extra work. Department called upon him to discuss the matter
well as settlement of remaining extra work dispute. The petitioner revised the rate, however, did not settle the extra work dispute. Hence, the confirmation given ... employer in settling the claims for extra work or that the alleged failure to pay for the extra work did or could have furnished
original tender, the contractor cannot claim any extra rate. He can claim extra rate only if that class of work is not provided ... fact that the grievance of the contractor was to claim extra charges for extra work. Department called upon him to discuss the matter
civil work which was
assigned to the plaintiff and those changes involved extra
work and extra price implications. Some other extra works
were later entrusted ... extra works for the
defendant; (2) extra works executed by him were accepted
by the defendant and (3) he had not executed extra work
gratuitously
additional claims and have
offered to revise the work order value to Rs. 25.50 cr. including
the additional claim for extra work, as a full ... GDCL") for execution of
work under Work Order No. D/CE/003840 dated 01.08.2015 for
OHE works and Work Order No. D/CE/003841
additional claims and have
offered to revise the work order value to Rs. 25.50 cr. including
the additional claim for extra work, as a full ... GDCL") for execution of
work under Work Order No. D/CE/003840 dated 01.08.2015 for
OHE works and Work Order No. D/CE/003841
additional claims and have
offered to revise the work order value to Rs. 25.50 cr. including
the additional claim for extra work, as a full ... GDCL") for execution of
work under Work Order No. D/CE/003840 dated 01.08.2015 for
OHE works and Work Order No. D/CE/003841
awarding claims for the extra work under the heads of Basement
Extra Work, PCC work done as per drawing, claim payable
towards mumty and machine ... amount of Rs.5,33,476/- for basement extra work. The
respondents have disputed this extra work on the ground
that there is no explanation
extra work, therefore, the appellant is not entitled
to any amount under the head of extra work. With respect
to claims ... respondents in their statement of
claim and, therefore, the contention that since the claim
for extra work performed by the appellant has been
admitted