employed only in the following
types of cases
.
(a) Casual Labour (Open Line).- Casual labour are primarily engaged to
supplement the regular staff in work ... engaged on Railways
for execution of Railway projects, such as new lines, doubling, conversion,
construction of building, track Renewals, Route Relay interlocking Railway
Electrification, Setting
Express Newspapers Pvt. Ltd. & Ors vs Union Of India & Ors on 7 October
common sense practical way rather
than on theoretical and theocratic grounds.
Conversion brings many complexities in its train, for it
imports a complex composite composed ... going laxness and tolerance which makes the
conversion only nominal. There is no clear out dividing
line and it is not a matter which
Pondicherry
Coastal aquaculture units are
situated within 500 m of high Tide
Line of the sea. This is not in
consonance with ... coastal
aquaculture units which infringes
the fundamental rights to life and
livelihood.
Conversion of agricultural farms
and salt making lands into
commercial aquaculture farms
respondents-con-
tractors to carry out work of excavation, conversion of
over-head electric lines and laying of underground cables
under public roads ... engages var-
ious contractors to carry out work of excavation, conversion
of overhead electric lines and laying of underground cables
under public roads, as well
Dhian Singh Sobha Singh & Another vs The Union Of India on 29 October, 1957
supply from a 11
KV line. The said circular stipulated that surcharge would continue to be
levied till conversion of supply ... load/demand exceeding 5000 KW/KVA and running at
11 KV till conversion of supply to 33 KV or higher
voltage. The matter has been
prior to
June 1995 draw power from 11 KV High Tension Supply
Line. Electricity in the State of Punjab, where the
industrial units are located ... cost of conversion to disincentivise the
consumers from continuing to receive supply on the 11 KV
transmission lines. It is on the aforesaid basis that
Lord Wrenbury (ibid., 563), and the long line of cases of buyers who sue sellers for conversion of, or for failure to deliver, goods bargained
taken to install bird diverters pending consideration of the
conversion of overhead power lines into underground power lines. Moreover, the
court directed that ... which it is not
feasible to convert all transmission lines into underground power transmission lines:
a. In view of the diverse factors responsible