Pristine Logistics & Infra Projects ... vs Eta Engineering Pvt. Ltd. & Ors. on 19 April, 2016
Author: Manmohan Singh
Bench: Manmohan Singh
* IN THE HIGH ... 19th April, 2016
+ Arb.P.No. 255/2015
PRISTINE LOGISTICS & INFRA PROJECTS PVT. LTD. & ANR
..... Petitioners
Through Mr.M.S.Ganesh
represented himself to be the Regional Manager of M/s.Integrated Project Logistics Ltd., and the said statement was acknowledged ... Jayachandran, the Managing Director of M/s.Integrated Project Logistics Ltd, Chennai. They represented that the Head Office of the said Compnay
Pristine Logistics And Infra Projects ... vs Eta Engineering Pvt. Ltd. . on 1 August, 2016
Bench: Shiva Kirti Singh , R. Banumathi
ITEM NO.32 COURT ... High Court Of Delhi At New
Delhi)
PRISTINE LOGISTICS AND INFRA PROJECTS PVT. LTD. AND ANR.
Petitioner(s)
VERSUS
ETA ENGINEERING
business of exports,
imports, deemed exports, third country trading, arranging
finance, logistics, project exports and management. The
respondent company had filed 18 complaint cases under
Dated this the 30th day of April, 2016
Plaintiff: M/s LCL Logistics (India) Pvt.Ltd.,
(Formerly known as LCL Agencies
(India ... freight and Air freight, container freight station
warehousing services, project logistics and other similar
business relating to air freight, maritime and logistics
industry, having
petitioner in connection with the said
Arbeel project for the respondent. The project could not, however,
materialize for no fault of the petitioner. That ... rendered
various services to the respondent for facilitating execution of the
project including logistic support at Amman/Jordon. The petitioner submits
that the Service Provider
petitioner in
connection with the said Arbeel project for the respondent. The
project could not, however, materialize for no fault of the petitioner.
That ... rendered various services to the respondent for facilitating execution
of the project including logistic support at Amman/Jordon. The
petitioner submits that the Service Provider
exempted services. It is seen that jetty was to handle the logistics of project Cargo and equipment for setting up an onshore Gas Terminal; they
Contracts. The Project Office was only used for the purposes of correspondence
and as a communication channel; apart from that, the Project Office ... other
business of the Assessee was carried on through the Project Office. The Project
Office was manned by three employees; (i) Ravi K. Prabhakar
equipments, installation tools and tackles,
consumables, labour, logistic supplies, planning, engineering,
documentation, etc. to fulfil the project specifications upto the
commissioning stage." Under Clause ... logistic
supplies, planning, engineering, documentation etc". Further under Clause
3.1.3 the Petitioner was made responsible for taking over all the IOCL
supplied project materials