leaving an uncovered deficit of
Rs. 343 crores, resulting in cash flow problem for the
Appellant. On the other hand, the Generation and
Transmission Utilities ... view, is not in order as it may create a problem of
cash flow for the distribution licensees which are
already burdened with heavy debts
licensee
network from the captive production unit may give rise to
accounting problem is an artificial distinction and is not
reasonable classification to permit discrimination ... date of commissioning on the
assumption that there may be accounting problems.
h. The said classification neglects the fact that there is no direct
feeding
issued by the State Load Despatch Centre stating that there
was evacuation problem and that the State Load Despatch Centre
could not permit synchronisation
which is an uncontrollable
cost, results in serious cash flow and financial
problem for the respondent no.1 affecting the
maintenance of the distribution system ... possible in
terms of the Tariff Policy to avoid cash flow
problem to the distribution licensee.
9.10. It has to be noted that the authority
would be convened by
the APTRANSCO (R-2) for discussing the pending
problems and requesting the Appellant not to press for
reference to arbitration till ... Arbitration stating that a meeting will be convened for
discussing the pending problems. Accordingly, the
Appellant nominated its Company Secretary Mr. D
Krishna
Appeal No.35 of 2012
also create right of way related problems. Laying of 66 kV
transmission line is also not feasible for many existing ... voltage of 66 kV without
considering the practical problems with respect to supply
to the existing consumers and the substantial expenditure
required for such change
M/S. Sls Power Limited vs Andhra Pradesh Electricity Regulatory ... on 20 December, 2012
Appeal
M/S Dlf Utilities Limited vs Haryana Electricity Regulatory ... on 3 October, 2012
Appeal No
been under forced shutdown since
25.09.2011 due to turbine rotor problem.
d. The Commission attempted to strike a balance between the
interest of the consumers
with respect to PLF and other parameters
and should get fixed the problem so that loss of generation is
minimized. The PLF of PTPS Unit