that GRIDCO has admitted that delay in land acquisition
was a general problem, is misconceived. The Appellant was
required to explain delay through CPM (Critical ... over to the Appellant by 11.2.2010. Accordingly, the alleged
law and order problem in May, 2010 and afterwards did not have
effect on acquisition
last piece of land could be acquired.
3. Then, came the problem of "Jantri" rates. On 1.4.2011, the Govt.
of Gujarat issued ... Then, came the problem of what is called 'NA permission'
meaning permission for conversion of agricultural land into industrial
group of the
distribution licensees would culminate into practical
solutions to the problem of such supply effected by HT
Industrial and Commercial category consumer throughout ... been denied by the distribution licensee and that they are
facing problems because of the same.
f) One Sai Erectors took connection in their individual
November, 2009, but was
commissioned only in November, 2011 due to problems in OLTC
imported from ABB, Sweden.
4. According to the appellant, the appellant ... noted that the commissioning of Spare Transformer got
delayed due to transportation problem. The new set of OLTC was procured by the
BHEL from
coal companies which is
beyond the control of the Appellant. The problem due
to poor quality of coal further aggravated during
monsoon season ... choking problems caused by
usage of wet, sticky and muddy coal leading to poor
plant load factor which in turn results in high
auxiliary consumption
stiff
resistance from the farmers leading to serious
law and order problems. Despite this, the
Respondents have taken substantial steps in
metering the un-metered ... facing stiff
resistance from the farmers leading to serious law and
order problems in view of the non co-operation of the un-
metered agricultural
borne by the
Appellant.
xxiv) They further contend if the problem in relation to getting coal supply
post tie up of the fuel linkage ... while considering allotment of coal blocks in the country so that
similar problems do not arise in future. Appellant further contends,
EAC also observed that
backing
down of the generation due to transmission
constraints and grid problems. This is purely due to
non availability of evacuation of intra-structure ... grid problems which is beyond the control of the wind
energy generators. The State Commission failed to
consider this aspect while deciding the normative
plant
GETCO had not wanted the commercial
operation because of any problem.
12.13 that the State Commission erred in holding that GETCO declared
Commercial Operation ... more than three
months from 25.04.2011 because of interruptions, tripping and other
problems in the line. The interruptions, tripping etc. alleged had nothing
various associated components as mentioned
earlier. It is observed that these problems were resolved only after
several meetings between M/s Indure and NTPC ... Appellant, if completed the project
in time, could not have faced the problem of cooling water supply from
Farakka Barrage at that point of time