present writ petition challenges the Delhi Electricity Regulatory
Commission (Renewable Purchase Obligation and Renewable Energy
Certificate Framework Implementation) Regulations, 2021 ("Regulations ... Amendment)
Order, 2021 ("Order"), which inter alia increase the renewable purchase
obligations and imposed additional surcharges. The Petitioner contends that
the changes introduced
resulted in injury
to the Discoms for failure to fulfill the renewable purchase
obligation with the Discoms. The liquidated damages
provided under the Clause ... also result in injury to
discoms for failure to fulfilment of Renewable Purchase Obligation
(RPO) with them. The respondent thus suffered tangible and
intangible losses
resulted in injury
to the Discoms for failure to fulfill the renewable purchase
obligation with the Discoms. The liquidated damages
provided under the Clause ... also result in injury to
discoms for failure to fulfilment of Renewable Purchase Obligation
(RPO) with them. The respondent thus suffered tangible and
intangible losses
obligation to renew the MDA by serving on the other party
prior notice of 6 months. The clause obliges the party giving the notice ... Master Dealer's aggregated purchase of Products fails to fulfil the minimum
purchase obligations for that year as defined in clause
took the contract of purchase of Tendu leaves for the year 1970 from the Government and sought renewal of the contract for subsequent years ... cannot beused solely for the purpose of enforcing the contractual rights or obligations. But necessarily the enforcement is for enforcing the fundamental rights or statutory
specifically asked if the renewal option was exercised after three years in 1994 and we were informed that no renewal option was exercised. We were ... purchase of a system on deferred payment of purchase price (1) Whether there is any binding obligation on the hirer to purchase the goods
Solitaire Ventures Pvt Ltd & Ors vs Vipul Sez Developers Pvt Ltd & Others on
Singapore Union Line Pvt. Limited, Singapore for a period of three years, renewable on satisfactory performance for another two years. According to this letter ... maximum number of vessels. There will be specific obligations on the part of Indian Charterer to purchase a stipulated number of vessels before