Sail Ex-Employees Association vs Steel Authority Of India Ltd And Anr. on 13 August, 2009
Author: V.K.Jain
Bench: V.K.Jain ... 2254/2002
Reserved on: 7th August, 2009
Pronounced on: 13th August, 2009
# SAIL EX-EMPLOYEES ASSOCIATION .......Petitioner
! Through: None
VERSUS
$ STEEL AUTHORITY OF INDIA
MURALIDHAR
JUDGMENT
18.04.2012
Introduction
1. The Steel Authority of India Limited ('SAIL'), in this petition under
Section 34 of the Arbitration and Conciliation ... Manesmann
International GMBH ('SI') and dismissing the counter claims of SAIL.
Third member of the Tribunal passed a minority/dissenting award on 10th
directly from Steel Authority of India Limited (hereinafter referred to
as the „SAIL‟) in respect of all their requirements other than those funded
from ... pursuant to a Memorandum of
Understanding signed between Ministry of Railways and SAIL for all the
purchases made for the Indian Railways. However, in respect
Vijai Kumar Ajay Kumar And Another vs Steel Authority Of India Limited (Sail) ... on 4 May, 1993
Equivalent citations: AIR1994ALL182, AIR 1994 ALLAHABAD ... handlers to favour the contractors already handling the iron and steel of SAIL, Further contention is that the similar condition was imposed by the respondents
Gupta, Sr. Advocate,
Mr. Arjun Ray Mukherjee,
Ms. Saheli Mukherjee.
...For the SAIL.
Mr. Kishore Datta, Sr. Advocate,
Mr. Neelesh Choudhury,
Ms. Anuradha Poddar ... Respondent No. 2, M/s Steel Authority of India Limited (SAIL). About
five bidders, namely, Praxair India Private Limited (the writ petitioner),
Ellenbarrie Industrial Gases
Steel Authority of India Ltd. (hereinafter referred to as "SAIL") had
preferred the instant application under Section 34 of the Arbitration and
Conciliation ... Short Term of Agreement are hereby set out :
Clause 1.2-Applicable to SAIL:
a) Assurance on Cargo and Cargo volume: SAIL assures and import
cargo
2014 Page 4 of 43
Authority of India Limited (‗SAIL') and Rashtriya Ispat Nigam Limited
(‗RINL'). Even in respect of the contracts with ... parties reference was constantly made to the separate agreements Anglo had
with SAIL and RINL. There was an Empowered Joint Committee (‗EJC')
that
submitted, that
3
exorbitantly high amount has been fixed by the SAIL for renewal of
lease on the basis of assessment made by a Company ... Commercial Plot, but it is
within the knowledge of Bokaro Steel Limited / SAIL that
residential-cum-commercial maps were sanctioned and there was no
objection
herein are the Steel Authority of India Limited (popularly known as 'SAIL' and to be referred to as such for brevity ... instrumentality of its, which is the present respondent No. 1, the SAIL. It was no longer in controversy before us that it is a department
Steel Authority of India Limited "(in short SAIL)" is a public sector company and is an integrated iron and steel producer in India ... Plant" (in short SSP) is a plant of the first respondent SAIL which manufactures steel and allied products. The third respondent is the Deputy