authority on the basis of the recommendation of the EAC or the SEAC, as the
case may be, at the preliminary stage itself, prior ... required before any construction work, or preparation of land (except for
38 SEAC
39 SPCB
40 UTPCC
27
PART C
securing the land) is started
Forest land
G.3 Trees
G.4 Pipeline
H Appraisal by the SEAC
I Courts and the environment
J Directions
2
PART A
A Introduction ... notification
10
ToR
11
SEAC
4
PART A
December 2009 and February 2010. The final EIA report was placed before the
SEAC and the SEIAA
short, “the EP Act ”
7
In short, “Central SEAC”
8
In short, “EIA 2006 Notification”
9
In short, “EIA 2014 Notification ... categorically clarified that the scrutiny conducted
at the State Level by SEIAA / SEAC is of the same rigour as that undertaken by
the Central
Pending further proceedings before the NGT, the State Expert
Appraisal Committee (SEAC) considered the draft DSR and
accorded its approval on 03.05.2024 and then ... Committees:
The same Expert Appraisal Committees (EACs) at the Central
Government and SEACs (hereinafter referred to as the (EAC) and
(SEAC) at the State
State Level Environment Impact Assessment Authority
3
CPC B
4
EC
5
SEAC
2
for Maharashtra6, based on the recommendations of the SEAC granted ... secure an EC from the SEIAA, based on the
recommendations of the SEAC. Where a project falls within the parameters
stipulated in the Schedule, paragraph
examination and
evaluation by the State Expert Appraisal
Committee (SEAC) having regarding to the fact
that the SEIAA comprises of
technical/scientific experts. The SEAC ... holding that unless the State
Expert Appraisal Committee (hereinafter referred to as “SEAC”)
and the State Environment Impact Assessment Authority
(hereinafter referred to as “SEIAA
Union Territory Level Expert Appraisal Committee ( for short
Page 4 of 39
‘SEAC’) as to be constituted following the Notification and in the
absence ... regulatory authority shall consider the recommendations of
the EAC or SEAC concerned and convey its decision to the
applicant within forty five days
State
Expert Appraisal Committee (hereinafter referred to as the
“SEAC”), the proposal of the appellant came to be considered.
The relevant part of the said ... Enviro Labs & Consultants, Hyderabad
attended and made a presentation before the SEAC.
It is noted that the mine lease area is 24.00 Ha.
which
Section 3 of the EP Act.
It further provided that the SEACs would examine as to
whether under the prevailing laws, the project is permissible ... said notification also clearly
provided that where the findings of the SEACs are negative,
closure of the project would be recommended along with other
actions
concerned District shall forward the same
for examination and evaluation by the
SEAC. The same shall be examined by the
SEAC within a period ... Needless to state that while preparing
DSRs and the appraisal thereof by SEAC
and SEIAA, it should be ensured that a
strict adherence