soil testing in order to know the condition of the soil. The soil testing report regarding the condition of soil was obtained by the claimant ... soil, water conditions or about soil pressure to be encountered. The tenderer who was to give bid, was at liberty to conduct sub soil testing
found twelve employees present besides he saw a number of soil testing machines present in the basement. He had found one Shri S.Kashyap, consultant ... stated that he did not remember the exact number of soil testing machines but the number could be four. He also mentioned in cross-examination
faced difficulties due to "incomplete and inadequate report of the soil
testing based on SPT". According to the petitioner, the Soil Testing
Agency ... proceeded to submit Soil Testing Report based on "special
penetration test for foundation purpose and not for HDD works".
11. The response given
Architect recommended a payment of
Rs.15,000 on account of soil testing which
the respondent has since admitted.
O.M.P. No.1588/2014 ... construction of drains.
Claim of Rs 15,000/- on account of
soil testing is admitted by the respondent.
regarding electricity, the respondent argued
that there
Contract, the respondent no.1 had to take a Soil Testing Report from a
reputed agency and also give approved structural designs and drawings from ... contractor
was also asked to prepare designs and drawings after soil testing and to
submit the same. Consequent thereupon soil investigation were
undertaken, designs
soil, water conditions
or about soil pressure to be encountered. The tenderer who
was to give bid, was at liberty to conduct sub soil testing ... that the work involved below ground construction and
sub soil structure for which proper soil testing and knowing
the nature of soil was necessary
that before the
accident, the Injured was doing the work of soil testing, which required
extensive travel and for the purpose of soil testing, Injured ... accident in question, he cannot do the work of soil testing and after this
accident, Injured had opened a shop, which went into losses
Sports Injury
Centre for the Commonwealth Games 2010 and as such soil test with
respect thereto was permitted to be carried out. On 16th November
work was
completed by it by December, 2006 except for soil testing
which took another five months as clear site was not made
available
which was
provided by NDAL. This involved various processes starting with
soil testing and evaluation of available data, after which the
foreign technical personnel assessed