respondent. The petitioner had to
postpone the date in view of the Tsunami tragedy and permission to hold the
meeting on a subsequent date ... Union Finance Minister with reference to the relief works for the Tsunami
victims and therefore, the Congress Party has the right and duty to explain
Failure to assess and prepare for impact of cyclonic storms and tsunamis on the seawater intake structures for coolant and desalination;
xiii.Post facto issue ... been selected in a place which is not prone for earthquake or tsunami.
12.3. It is stated that worldwide there are 529 Atomic Power Stations
purpose of providing house sites to Tsunami affected victims dispensing with the enquiry under Section 5-A of the Act thereby the petitioners were deprived ... urgency in acquiring the lands for rehabilitation of victims of Tsunami at an early date; that Tsunami caused massive destruction on 26.12.2004, whereas, the respondents
matter of manufacture and supply of webbings to fishermen affected by Tsunami.
2. According to the petitioner ... webbings to be supplied to the fishermen affected by the Tsunami. Therefore, the Re-Tender Notification is vitiated by non-application of mind and arbitrariness
Tamil Nadu
Rep. By its Secretary
Rural Development and Panchayat Raj Department
Tsunami District Implementation Unit,
Chennai-600 001.
2.The Project Director,
Project Director ... Office,
Tsunami Project Implementation Unit,
Clive Battery,
Nos.4 & 4A, Rajaji Salai,
Chennai-600 001.
3.The District Collector/Chairman,
Tsunami District Implementation Unit
further aver that on 11.3.2011, there was an earthquake followed by a Tsunami, at Fukushima Dai-ichi Plant in Japan, which resulted in evacuation ... India, New Delhi, and would submit that in the event of Tsunami or Earthquake, the spent fuel, which is being stored at MAPS, would
Counsel
for Mr.R.Parthiban
JUDGMENT
R.SUDHAKAR,J.
Eleven years after tsunami wreaked havoc along the coasts of India and other South-East Asian ... moot question raised for consideration before us is as to whether tsunami is an insurable risk or not.
2. Aggrieved by the order dated
address and resolve the
delirious effects and consequences of the Tsunami that had struck the Indian
coast on 26.12.2004, leaving lakhs of persons in need ... repair and reconstruction of houses which have
been damaged or by tsunami, and (ii) construction of new houses
in resettlement areas; through, inter alia, provision
follows:
In December 2004, Karukalacherry fishermen village,
Karaikal is one of the Tsunami affected area. After Tsunami, both the
Central and the Union Government ... some of the
NGOs have come forward to give assistance to the Tsunami affected
village. At the time, the accused
cement and steel utilized in the construction of the houses for Tsunami affected persons.
(2)Whether the Notification No.32/2005-CE dated ... duty paid on cement and steel utilized in the manufacture of Tsunami houses.
(3)Whether the restriction imposed by the first appellate authority, confirmed