required to obtain prior consent of the flat takers as long as
builder puts up additional construction in accordance with the layout plan,
building rules ... consent is given by the purchaser of the flat for
additional construction in the agreement itself, there is no necessity to
obtain a fresh consent
requires the permission of 2/3rds of the flat purchasers for
putting up any such additional construction ... Plaintiff - Society
represents 309 flat purchasers. Even if one flat purchaser was to
object to the additional construction, the Developer would have been
prohibited from
purchasers who purchased their respective
units/flats in the said entire additional construction. A further
injunction was prayed to restrain the Corporation and its officers ... amendment in respect of any construction of additional
structures; however, the right to make any construction of additional
structures/buildings would come into existence only
requires the permission of 2/3rds of the flat purchasers for
putting up any such additional construction ... Plaintiff - Society
represents 309 flat purchasers. Even if one flat purchaser was to
object to the additional construction, the Developer would have been
prohibited from
additional building
provided the construction forms part of a scheme or a project.
That construction has to be in accordance with layout plan.
That construction ... when he sales the flats. No consent of the
flat owners is necessary for raising additional
structures. But if the additional structures
whether prior consent of the flat takers was required to be taken to put
up additional construction. The Apex Court in the said judgment held ... required to obtain prior consent of the flat takers as
long as the builder puts up additional construction in accordance with the lay
out plan
whether prior consent of the flat takers was required to be taken to put
up additional construction. The Apex Court in the said judgment held ... required to obtain prior consent of the flat takers as
long as the builder puts up additional construction in accordance with the lay
out plan
under the agreement with the flat purchasers. The flat purchasers
never objected to the proposed additional construction. The original
plaintiff ... flat
purchaser will not create any obstruction. The said Clause cannot
constitute a consent by the flat purchasers for construction of
additional floors
under the agreement with the flat purchasers. The flat purchasers
never objected to the proposed additional construction. The original
plaintiff ... flat
purchaser will not create any obstruction. The said Clause cannot
constitute a consent by the flat purchasers for construction of
additional floors
make additional construction in the front and rear open space to the existing ground floor level. The first floor allottees were permitted additional construction ... Nagar, Chennai and he had not put up any additional construction in and around the flat more particularly in the common land. Also that