notification dated
28.08.2015 and Amendment in section 12 read with
amended Schedule 5 and Schedule 7 based on
Arbitration and Conciliation (Amendment) Act 2015,
suffers ... Arbitrator and the same is therefore violative of
section 12 of the Arbitration and Conciliation Act,
1996 (as amended in 2015) and runs contrary
follow the mandatory
procedure prescribed under Section 31(3) of the
Arbitration Act, 1996.
AS.12/2018
10
18) 1st Defendant contends that, the land ... Section 28(1)(a) of the Arbitration
Act, 1996 mandates that the Arbitral Tribunal shall
decide the dispute submitted to arbitration in
AS.12/2018
under Sections 37(1) and 37(2) of the Arbitration and
Conciliation Act, 1996 against the order and executable order made in
Arbitration ... award only on the grounds enumerated under Section 34(2) of the
Arbitration Act.
12.Mr.Su.Srinivasan, in support of his contentions, relied upon
land
acquisition matters?
12) Before proceeding further it would be apt to extract Sec. 34
and Sec. 37 of Arbitration and Conciliation Act, 1996, which ... Hindustan Copper Limited2 , in paragraph
12 of the judgment held as under:
"12. Section 34 of the Arbitration and Conciliation Act, 1996
corresponds
Section (1) of Section 29A of the Arbitration and Conciliation Act 1996, the award shall be made within a period of 12 months from ... Central Government. The petitioners have filed their application under sub Section (5) of Section 3G of the National Highways Act, 1956 on 13.06.2017. More than
Section 29A of the Arbitration and Conciliation Act, 1996 hereinafter called the Act, 1996 provides as under:-
" Section 29 A of the Arbitration ... period of 12 months from the date the arbitral tribunal enters upon reference."
Thus, sub Section (5) of Section 3G of the National Highways
under the provisions of the Arbitration
Act, 1940 , which did not have a provision similar to
the provisions of Section ... award to each of the parties before
him.
12. Section 34 of the Arbitration and Conciliation
Act, 1996 reads as follows:
9
34. Application
Section 29A of the Arbitration and Conciliation Act, 1996 hereinafter called the Act, 1996 provides as under:-
" Section 29 A of the Arbitration ... period of 12 months from the date the arbitral tribunal enters upon reference."
Thus, sub Section (5) of Section 3G of the National Highways
Section 29A of the Arbitration and Conciliation Act, 1996 hereinafter called the Act, 1996 provides as under:-
" Section 29 A of the Arbitration ... period of 12 months from the date the arbitral tribunal enters upon reference."
Thus, sub Section (5) of Section 3G of the National Highways
Section 29A of the Arbitration and Conciliation Act, 1996 hereinafter called the Act, 1996 provides as under:-
" Section 29 A of the Arbitration ... period of 12 months from the date the arbitral tribunal enters upon reference."
Thus, sub Section (5) of Section 3G of the National Highways