outstanding loan dues up to 31.07.2013 availed
by them for the BOT project from their
Bankers/Financial Institutions/Agencies.
3. The Central Preventive Unit ... outstanding loan dues
up to 31.07.2013 availed by them for the BOT project
from the Banks and Financial Institutions/Agencies.
Page 8 of 10
Appeal
maintain a project relating to
construction operation and maintenance of Paradip Port
connectivity project under the Build Operate Transfer (BOT) basis.
For this purpose ... assessee on built, operate and transfer basis (BOT).
BOT is a form of project financing wherein a private entity
receives a concession from the public
treated the purchase
and use of construction materials for its ongoing BOT projects as
involving deemed sales. In the absence of any recorded sale ... finally argued that the petitioner is not
disputing that in the BOT project the the petitioner is not liable to pay
commercial and entry
treated the purchase
and use of construction materials for its ongoing BOT projects as
involving deemed sales. In the absence of any recorded sale ... finally argued that the petitioner is not
disputing that in the BOT project the the petitioner is not liable to pay
commercial and entry
treated the purchase
and use of construction materials for its ongoing BOT projects as
involving deemed sales. In the absence of any recorded sale ... finally argued that the petitioner is not
disputing that in the BOT project the the petitioner is not liable to pay
commercial and entry
treated the purchase
and use of construction materials for its ongoing BOT projects as
involving deemed sales. In the absence of any recorded sale ... finally argued that the petitioner is not
disputing that in the BOT project the the petitioner is not liable to pay
commercial and entry
under:
10. The appellant company had been functioning as a BOT project
Manager for the bus terminal cum shopping complexes at different KSRTC
stations ... office complex called "Trans Towers" for
KSRTC. This BOT projects were constructed as a Joint Venture of the
assessee with KSRTC. The appellant
years and 6 months, commencing from 21.06.2002
5
Project
6
The Agreement
7
BOT
FAO(OS) 38/2018 & FAO(OS) (COMM) 69/2018
Signature ... Mapex, as the
Concessionaire, was authorized to implement, operate, and
maintain the project facilities in accordance with the terms of
the Agreement.
(c) Subsequently, Mapex
known
and unknown FIRs lodged against petitioner arising out of Bike Bot
Project in State of Madhya Pradesh. Petitioner has made a prayer of
following ... application named BIKEBOT
and investments scheme in name of Bike Bot Project whereby any
person could invest total amount of Rs.62,100/- for period
petitioner company
to Build, Operate and Transfer (BOT) the Jatayupara Tourism
Project for 30 years and to raise finances for completion ... submitted that Jatayapura Tourism Project
is a major BOT project contracted between the State of Kerala
and petitioners 1 and 5. When the BOT contract