case of the purchase of the houses which a builder undertakes to construct for the buyer, the purchase can be said ... transfer the booking of the said apartment despite the builder having failed to deliver possession and this Commission vide order dated 12.10.2015, having now directed
questions which require consideration in the appeal are
(i). Can a builder give alluring advertisement
promising delivery of possession of the constructed building/flat ... view, it is unfair trade practice on the part of the builder to collect money from
the prospective buyers without obtaining
the required permissions such
13th floor of Tower C measuring 1765 sq. ft. The Builder Buyers Agreement dated 22.08.2012 was entered into between the Complainant and the Opposite Parties ... paid a sum of ₹68,60,316/-. It is averred that the Builder Buyers Agreement was an already prepared Agreement with one sided terms
Cordcon Builders Pvt. Ltd. & Anr. vs Valerian Anthony Diago on 16 April, 2015
NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI FIRST APPEAL ... Complaint No. 38/2009 of the State Commission Maharastra) 1. CORDCON BUILDERS PVT. LTD. & ANR. REGISTERED OFFICE AT SAGAR CITY COMPLEX, V.P. ROAD
Somdutt Builders - Ncc (Jv), Hyderabad vs Acit, Hyderabad on 3 February, 2017
IN THE INCOME TAX APPELLATE TRIBUNAL
HYDERABAD BENCH "B", HYDERABAD
BEFORE ... 2009
Assessment Years: 2005-06 & 2006-07
Somdutt Builders - NCC (JV), vs. Asst. Commissioner of
Hyderabad. Income-tax, Circle - 6(1),
Hyderabad.
PAN - AAQFS
submitted by the learned counsel for the complainants that ordinarily big builders such as the OP in these cases, are contracting/sub-contracting the construction ... become the order of the day in the contracts designed by big builders, a person seeking to buy an apartment is left with no option
acquisition of their land, in front of the projects of various builders also halted the construction work and there was default in payment of installments ... Greater Noida. It is further stated in the rejoinder that several builders including the opposite party itself had completed and delivered other projects
owners sold their 20 per cent share to M/s. United Builders. During the previous year relevant to assessment year 1997-98, the assessee converted ... development and concession (sic) of building started jointly with M/s. United Builders as per the agreement entered into by them. It was agreed
Samia International Builders (P) ... vs Neeta Rani on 3 November, 2015
NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION NEW DELHI FIRST APPEAL NO. 630 OF 2015 (Against ... 2012 of the State Commission Delhi) 1. M/S. SAMIA INTERNATIONAL BUILDERS (P) LTD. THROUGH ITS DIRECTOR, MR. JAMIL A. KHAN, SAMIAH HOUSE
home loan, further payments would only be made after the builder
credits interest and on handing over of the project.
(2.6) According to the informants ... compounded quarterly. On the other hand, any delay by the builder in
completion of the project only entails a penalty