only
after the construction of the factory building within the specified time and
obtaining building completion certificate from Executive Engineer of
respondent ... legal
interest. The said agreement provided that construction of building and
obtaining building completion certificate has to be completed within a
period of two years
construction in
all respect and obtain the occupation certificate including part
occupation certificate and building completion certificate. The
agreement entered into between the parties ... building completion certificate and occupation certificate.
The condition imposed by the respondent against the claimant to obtain
occupation certificate and building completion certificate
construction in
all respect and obtain the occupation certificate including part
occupation certificate and building completion certificate. The
agreement entered into between the parties ... building completion certificate and occupation certificate.
The condition imposed by the respondent against the claimant to obtain
occupation certificate and building completion certificate
received from MCGM that Building Completion Certificate/Occupation Certificate had
not been issued to the assessee, and accordingly, the building had not been completed till ... Building Completion Certificate; one set of completion plans on canvas; Structural
engineer's completion with plans; and Site supervisors completion certificate, a request
case of the petitioner that QCI
did not insist upon the Building Completion Certificate from the petitioner and vide its
decision dated July ... application shall be taken only
after receipt of the Building Completion Certificate. The petitioner would contend that on
July 19, 2016, it had already submitted
prayer is also sought directing respondent No. 1 to accept Building Completion Certificate dated 11th April, 1989 issued by the Area Manager of respondent ... that the building has been completed in 1976." According to the deponent, it would not amount to a Building Completion Certificate
Society, original Deed of Conveyance, property card, original IOD, Commencement Certificate, Occupancy Certificate, Building Completion Certificate, Draft Plan, along with all other necessary documents ... Complainant and to hand over the original IOD, Commencement Certificate , Occupancy Certificate, Building Completion Certificate, approved completion plans along with all other necessary documents
them necessary documents like
sanctioned plan, copy of the Commencement Certificate, Occupancy
Certificate, Building Completion Certificate, list of persons
who have purchased flats from ... original Deed of Conveyance &
Property Card, original IOD, Commencement Certificate, Occupancy
Certificate, Building Completion Certificate, approved plans
alongwith all other necessary documents and certificate
Occupancy Certificate
(hereafter "the O.C.", for short) and Building Completion
Certificate (hereafter "the B.C.C.", for short) in respect ... Respondent Nos.2 to 4 to
grant the Occupancy Certificate and Building Completion
Certificate to Petitioner No.1 in respect of the said
Building
admitted position that in order to obtain the
building completion certificate, Defendant No.1 submitted to Defendant
No.2 the "as built" drawings ... 2019 03:22:42 :::
S.5111.94.doc
checked and the building completion certificate was issued. He has
submitted that the Plaintiff has merely relied