third respondent had not extended any
portion in the subject building and the building plan was intimated by the
builder much earlier ... regularization of the subject property by paying necessary fees under the
building regularisation scheme 2017 vide application no.113C/567/2021 and
also enclosed
respondents to consider
the application filed by the petitioner under the Building REgularisation
Scheme 2017 for the subject property within a time frame. and after ... respondents to consider the
application filed by the petitioner under the Building Regularisation
Scheme 2017.
https://www.mhc.tn.gov.in/judis
Page
seeking direction to the
TANGEDCO to restore the electricity connection to
the building of the fourth respondent. This Court,
by order dated 07.11.2017, rejected ... direct the authority concerned before
whom the application for regularisation under the
DTCP Building Regularisation Scheme 2017 is
pending to decide the matter in accordance
Tamil Nadu Town and Country Planning Act of 1971 (under
building regularisation scheme-2017) before the 2nd respondent vide receipt
No.CMDA ... Tamil Nadu Town and Country Planning Act of
1971 (under building regularisation scheme-2017) before the 2nd respondent
vide receipt No.CMDA
violating the
building rules, constructed five storeyed building. The 4th respondent is running a
Government approved Liquor Bar at this building and without leaving ... authority concerned before whom the
application for regularization under the DTCP Building regularisation
Scheme 2017 is pending to decide the matter in accordance with
Petitioner
Vs
1 The Member Secretary
Chennai Metropolitan Development Authority
Thazamuthu Natrajan Building
No.1 Gandhi Irwin Road
Egmore, Chennai - 600 008.
2 The Commissioner ... Tamil Nadu Town and Country Planning Act of 1971 (under building
regularisation scheme - 2017) before the 1st respondent vide
receipt No.CMDA
seeking direction to the
TANGEDCO to restore the electricity connection to
the building of the fourth respondent. This Court,
by order dated 07.11.2017, rejected ... direct the authority concerned before
whom the application for regularisation under the
DTCP Building Regularisation Scheme 2017 is
pending to decide the matter in accordance
seeking direction to the
TANGEDCO to restore the electricity connection to
the building of the fourth respondent. This Court,
by order dated 07.11.2017, rejected ... direct the authority concerned before
whom the application for regularisation under the
DTCP Building Regularisation Scheme 2017 is
pending to decide the matter in accordance
seeking direction to the
TANGEDCO to restore the electricity connection to
the building of the fourth respondent. This Court,
by order dated 07.11.2017, rejected ... direct the authority concerned before
whom the application for regularisation under the
DTCP Building Regularisation Scheme 2017 is
pending to decide the matter in accordance
seeking direction to the TANGEDCO to restore the
electricity connection to the building of the fourth
respondent. This Court, by order dated 07.11.2017,
rejected ... direct the authority concerned before
whom the application for regularisation under the
DTCP Building Regularisation Scheme 2017 is
pending to decide the matter in accordance