Munirka Krishna Education Society vs Union Of India And Others on 6 August, 2013
As regards, the judgment which relied upon by
respondent No.2 in the case of St. Soldier Institute of
Pharmacy & Polytechnic (Supra), in that case, many
deficiencies have been found by the Expert Committee
including that the building itself was under construction.
However, in the present case, facts are altogether different
because in the inspection report dated 31.3.2013, it has been
found that the building was complete and the only bottle neck
was the construction of the all weather road, which was also
found to be there in the report. The arguments raised by
learned counsel for respondent No.2 was with regard to the
CWP No.8521 of 2013 -9-
library software that it has not been installed about which the
petitioner has also filed affidavit of the Secretary of the
Society which has remained un-controverted.