Eastern Railway vs Manjee Yadav & Ors on 25 June, 2024

16. The Division Bench judgment of this Court in case of Essem Enterprises (supra) was in relation to participation in the tender process where the appellant therein was adjudged as the lowest bidder and deposited the earnest money in terms of the condition of the tender. The validity of the bid extended beyond the period stipulated at the time of publishing the notice inviting tender which make 11 the appellant approach the Court. In the backdrop of the above, since he was adjudged as the lowest bidder, but for non-awarding the contract, damages was claimed under Section 74 of the Contract Act and it is held that the forfeiture condition in the contract is a standalone contract by itself and can be activated in the situation contemplated therein.
Calcutta High Court (Appellete Side) Cites 10 - Cited by 0 - H Tandon - Full Document