________________________________________________________ vs Collector Land Acquisition And Others on 20 April, 2023
5. In view of this, the application is allowed. The time for
completion of arbitration proceedings by learned Divisional
Commissioner, Mandi, in Reference Petition No. 1147 of 2018 titled
Dinesh Kumar and Ors. v. Collector Land Acquisition, is extended
by six months to be reckoned from the date parties appear before
learned Arbitrator. Parties are directed to appear before learned
Arbitrator on 17.5.2023.