Jorawar Singh vs Chandigarh Housing Board on 3 May, 2018
Sumer Singh Savant Vs. Chandigarh Housing Board's case (supra), as extracted in Para 20 of this judgment, no ground is made out for any compensation on account of delay in handing over of possession due to delay in start of construction on account of force majeure circumstances.