Search Results Page
Search Results
1 - 10 of 20 (2.77 seconds)Consumer Protection Act, 2019
Section 24 in The Consumer Protection Act, 1986 [Entire Act]
Section 24A in The Consumer Protection Act, 1986 [Entire Act]
Section 17 in The Consumer Protection Act, 1986 [Entire Act]
The Arbitration And Conciliation Act, 1996
Maneesh Jaikrishna & Anr. vs M/S. Unitech Limited on 2 May, 2016
"As far as the prohibition on use of underground
water in construction is concerned, the learned
counsel for the complainant has drawn my
attention to the order dated 21.08.2012 passed
by a Divisional Bench of Punjab & Haryana
High Court in Civil Writ Petition No. 20032 of
2008 wherein the High Court noted that the
public notice issued under Section 5(3) of the
Environment Protection Act, 1986 was published
in the newspaper on 26.12.2000. It further shows
that the said notice had imposed a complete ban
upon the use of underground water in the
construction without prior approval of the
competent authority. It was noted by the High
Court that despite publication of the aforesaid
notice, the builders continued to use
underground water for construction purposes. If
there was a complete ban on use of underground
CC 684/2016 Page 14 of 20
water for construction and the said prohibition
was notified on 26.12.2000, the opposite party
must have taken into account, the impact of the
said prohibition while entering into Buyers
Agreements with the complainants. Therefore, it
is not open to the opposite party to rely upon the
said prohibition in order to justify the delay in
construction of the villas sold to the
complainants. The opposite party knew at the
time of entering into agreements with the
complainants that it will not be able to use
underground water for construction of the villas
and therefore, will have to make alternative
arrangements from authorized sources for
making the water available for the said
construction. Therefore, the aforesaid
prohibition on use of the underground water for
construction purpose does not justify the delay in
completion of the construction. In any case, no
material has been placed by the opposite party
on record to show that efforts were made by it
during the relevant period to procure water from
alternative sources but it was unable to obtain
the water from the said sources. More
importantly, in the Buyers Agreement executed
between the parties, it was not disclosed to the
buyers that since no underground water can be
used for construction purpose, the developer will
have to arrange water from alternative sources
and in case it is not able to arrange water, the
construction would be delayed and in that case,
it will not be held responsible for the delay in
completion of the construction."
Wg. Cdr. Arifur Rahman Khan And Aleya ... vs Dlf Southern Homes Pvt. Ltd. (Now Known ... on 24 August, 2020
29. Having discussed the maintainability of the present complaint, the
next issue to be adjudicated is whether the Opposite Party No. 1 is
actually deficient in providing its services to the Complainant. The
expression Deficiency of Service has been dealt with by the Hon'ble
Apex Court in Arifur Rahman Khan and Ors. vs. DLF Southern
Homes Pvt. Ltd. and Ors. reported at (2020) 16 SCC 512, wherein it
has been held as follows:
Rohit Srivastava vs Paramount Villas Pvt. Ltd. & Anr. on 5 July, 2017
15. To strength the aforesaid findings, we tend to rely on Rohit
Srivastava v. Paramount Villas Pvt. Ltd. reported at 2017 SCC
OnLine NCDRC 1198, wherein it has been held as under: