1 - 10 of 22 (0.28 seconds)Rohan Builders (India) Private ... vs Berger Paints India Limited on 17 October, 2023
In the said
decision, the Court placed reliance on the decision of this Court in ATC
Telecom (supra), instead of the decision of the Calcutta High Court in
Rohan Builders (supra).
The Arbitration And Conciliation Act, 1996
Atc Telecom Infrastructure Private ... vs Bharat Sanchar Nigam Limited on 27 May, 2022
In the said
decision, the Court placed reliance on the decision of this Court in ATC
Telecom (supra), instead of the decision of the Calcutta High Court in
Rohan Builders (supra).
Section 14 in The Arbitration And Conciliation Act, 1996 [Entire Act]
Section 34 in The Arbitration And Conciliation Act, 1996 [Entire Act]
The Companies Act, 1956
Wadia Techno-Engineering Services ... vs Director General Of Married ... on 16 May, 2023
12. The instant issue was considered in Wadia Techno-Engineering
Services Limited v. Director General of Married Accommodation Project
(2023 SCC OnLine Del 2990) and ATC Telecom Infrastructure Pvt. Ltd. v.
Bharat Sanchar Nigam Ltd. [2023:DHC:8078]. These two decisions held
that the mandate can be extended "either prior to or after expiry of the
period so specified"1.
M/S Kmp Expressways Limited vs Idbi Bank Limited & Anr. & Ors. on 11 July, 2023
(ii) KMP Expressways Ltd. v. IDBI Bank Ltd. (2024:DHC:2739)
M/S.Suryadev Alloys And Power Pvt. Ltd vs M/S. Shri Govindaraja Textiles Pvt. Ltd on 13 September, 2019
In Suryadev Alloys and Power Pvt. Ltd. v. Shri Govindaraja Textiles
Pvt. Ltd. (2020 SCC OnLine Mad 7858) the Madras High Court also took a
similar view, and held that extension for making of the award may be
granted by the Court, even after the period under Section 29A(1) or Section
29A(3) of the 1996 Act has expired. However, after the award is passed, the
mandate cannot be extended in a petition under Section 34 of the 1996 Act.