Search Results Page

Search Results

1 - 10 of 14 (0.28 seconds)

State Of Kerala And Anr. vs N.E. Abraham on 5 February, 1998

361) and also by the Division Bench decision of the Kerala High Court in State of Kerala v. N.E.Abraham (1998(2) ILR Ker. 700). We are therefore, unable to accept the argument of Mr.Manimohan that the District Court exceeded its powers in interfering with the award of the arbitrator. The award of the arbitrator was substantially in conflict with the expressed provisions of the contract between the parties. It Arbitration Appeal Nos.4, 5, 6 & 7 of 2007 -39- was not within the powers of the arbitrator to award escalations in rates when the contract prevented award of such escalations on whatever reasons. There is no evidence in this case to hold that the company was in any way responsible for the delay caused on the side of the Contractor in completing the execution of the work. We therefore are of the view that the District Court was justified in interfering with the awards in O.P. Nos.55/02, 168/02 in full and with the award in O.P.8/02 in part.
Kerala High Court Cites 5 - Cited by 1 - Full Document

Venture Global Engineering vs Satyam Computer Services Ltd. & Anr on 10 January, 2008

The scope of section 34 of the Arbitration and Conciliation Act is again considered by the Supreme Court in Venture Global Engineering v. Satyam Computer Services Ltd. (2008 (4) SCC 190). Their lordships held inter alia under the above judgment that the aggrieved party is entitled to invoke right under Section 34 to have the award of the arbitrator set aside on the reason that the same is in conflict with the public policy of India. The public policy of India includes not only (a) the fundamental policy of India; or (b) the interest of India; or (c) justice or morality, but also the policy to interfere with anything which is patently illegal.
Supreme Court of India Cites 47 - Cited by 168 - P Sathasivam - Full Document

Numaligarh Refinery Ltd vs Daelim Industrial Company Ltd on 6 September, 2007

The judgment of the Supreme Court in Numaligarh Refinery Ltd. v. Daelim Industrial Co. Ltd. (2007(8) SCC 466) was in a case which involves a question whether it was Arbitration Appeal Nos.4, 5, 6 & 7 of 2007 -34- open to a contracting party to claim variation of the rates in the teeth of the provision of the contract that rates are firm and fixed. Their lordships held that once the price is fixed there is no provision for giving any benefit of fluctuation on the exchange rate in terms of the contract. Therefore, the expression firm and fixed is clear answer to the question that if during the course of contract certain fluctuations have taken place in the market on that count the claimant cannot raise extra demand on account of upward trend in the exchange rate.
Supreme Court of India Cites 13 - Cited by 90 - A K Mathur - Full Document

Mcdermott International Inc vs Burn Standard Co. Ltd. & Ors on 12 May, 2006

The judgment of the Supreme Court in McDermott International Inc. v. Burn Standard Co. Ltd. (2006(11) SCC 181) and Oil & Natural Gas Corporation Ltd. v. Saw Pipes Ltd. (2003(5) SCC 705) also deal with scope of the power of the court under Section 34(2) of the Arbitration Appeal Nos.4, 5, 6 & 7 of 2007 -35- Arbitration and Conciliation Act and keeping in mind the views expressed by the Supreme Court in those decisions it is not difficult to hold that the District Court under the impugned order did not transgress the limits of its powers under Section 34(2).
Supreme Court of India Cites 48 - Cited by 1325 - S B Sinha - Full Document

M/S. Gas Authority Of India Ltd. And Anr vs M/S. Keti Construction (I) Ltd. And Ors on 11 May, 2007

651) to argue that the District Court was not justified in its interpretation of the clause in the contract which provides that under no circumstances increase in rates will be allowed. According to him, there are other clauses in the Arbitration agreement which will justify award of higher rates and when these clauses are harmoniously interpreted it will be possible to sustain the award of the arbitrator. Mr.Manimohan relied on the judgment of the Supreme Court in Gas Authority of India Ltd. v. Keti Construction (I) Arbitration Appeal Nos.4, 5, 6 & 7 of 2007 -27- Ltd. (2007(5) SCC 38) to argue that a ground that Arbitral Tribunal has no jurisdiction to pass a particular award was not to be accepted lightly. In the instant case, the question of jurisdiction was not raised by the company at the appropriate time and that at any rate not pursued seriously in evidence. It is therefore, not open to the company to challenge the award of the Arbitrator on the ground of absence of jurisdiction in a proceeding under Section 34. Very strong reliance was placed by Mr.Manimohan on the judgment of the Supreme Court in K.N.Sathyapalan (Dead) By Lrs. v. State of kerala & Anr. (JT 2006(10) SC 615). On the authority of the above decision, the learned counsel argued that even when the terms of the contract does not provide for escalation of rates, once it becomes evident that the contractor Arbitration Appeal Nos.4, 5, 6 & 7 of 2007 -28- is unable to complete the work within the stipulated time and that to a certain extent at least the delay is attributable to certain actions or inactions on the part of the principal and also in cases where it becomes evident that the delay is due to unforeseen circumstances then there will be justification in awarding escalation. Mr.Manimohan placed reliance on the judgment of the Supreme Court in Food Corporation of India v. M/s Ahmed & Co. and Anr. (JT 2006 (10) SC 62)to argue that escalation of rates was normal and routine incident arising out of gap of time during inflationary period in performing any contact of any time. Hence, even in the absence of a clause in the contract permitting escalation in rates, escalation can be allowed once the evidence reveals that the delay in execution is at least to a Arbitration Appeal Nos.4, 5, 6 & 7 of 2007 -29- certain extent due to laches on the part of the principal.
Supreme Court of India Cites 13 - Cited by 34 - G P Mathur - Full Document

Ispat Engineering And Foundry Works, ... vs Steel Authority Of India Ltd. B.S. City, ... on 25 July, 2001

In Ispat Engineering & Foundry Works v. Steel Authority of India Ltd. (2001(6) SCC 347), it has been clearly held that the arbitrator has no authority or jurisdiction to abdicate the terms of the contract which actually incorporate of that party's desire while executing the contract. The arbitrator derives authority from the contract and if the arbitrator acts in manifest disregard of the contract the award passed by him would be an arbitrary one. In our view the District Court was justified in taking view that the award passed by Arbitration Appeal Nos.4, 5, 6 & 7 of 2007 -36- the Arbitrator to the extent it was in conflict with express terms of the contract was arbitrary and hence, liable to be interfered with under Section
Supreme Court of India Cites 11 - Cited by 139 - U C Banerjee - Full Document

Rajasthan State Mines & Minerals ... vs Eastern Engineering Enterprises & Anr on 20 September, 1999

34. The judgment of the Supreme Court in Rajasthan State Mines and Minerals Ltd. v. Eastern Engineering Enterprises (1999(3) Arb.L.R 350(SC), according to us, is apposite to the facts which obtain in these cases. The Supreme Court held therein that if there is a specific term of the contract which does not permit or give the arbitrator the power to decide the dispute or there is a specific bar under the Contract to the raising of a particular claim (underline supplied) then the award passed by the arbitrator in respect thereof will be excess of jurisdiction. The Supreme Court held that if the award passed by the arbitrator is disregarding the terms of the reference or the Arbitration Appeal Nos.4, 5, 6 & 7 of 2007 -37- arbitration agreement or the terms of the contract will be a jurisdictional error which is liable to be decided by the court under section 34.
Supreme Court of India Cites 20 - Cited by 335 - Full Document
1   2 Next