Search Results Page

Search Results

1 - 10 of 15 (0.24 seconds)

The Project Director National Highways ... vs M. Hakeem on 20 July, 2021

In this connection the decision of the Honourable Supreme Court in The Project Director, NHAI V. M. Hakim, (2021) 9 SCC 1 is invited wherein it was held that the power to set aside an Arbitral Award under Section 34 of the Arbitration And Conciliation Act, 1996 does not include the authority to modify the award. It further held that an award can be 'set aside' only on limited grounds as specified in Section 34 of the Act and it is not an appellate provision. It further held that an application under Section 34 for setting aside an award does not entail any challenge on _______________ https://www.mhc.tn.gov.in/judis Page No. 20 of 29 Arb.O.P.(Comm.Div.) No.434 of 2023 merits to an award.
Supreme Court of India Cites 72 - Cited by 299 - R F Nariman - Full Document

Ssangyong Engineering And ... vs National Highways Authority Of ... on 8 May, 2019

23. The Court held that the above ground is available only where the view taken by the Arbitral Tribunal is an impossible view while construing the contract between the parties or where the award of the tribunal lacks any reasons. The Court further held that an award can be set aside only if an arbitrator/arbitral tribunal decide(s) the question beyond the contract or beyond the terms of reference or if the finding arrived by the Arbitral Tribunal is based on no evidence or ignoring vital evidence or is based on documents taken as evidence without notice to the parties. _______________ https://www.mhc.tn.gov.in/judis Page No. 21 of 29 Arb.O.P.(Comm.Div.) No.434 of 2023
Supreme Court of India Cites 65 - Cited by 952 - R F Nariman - Full Document

Patel Engineering Ltd. vs North Eastern Electric Power ... on 22 May, 2020

24. The Honourable Supreme Court in Patel Engineering Ltd Vs. NEEPCO, (2020) 7 SCC 167 held that patent illegality as a ground for setting aside an award is available only if the decision of the arbitrator is found to be perverse or so irrational that no reasonable person would have arrived at the same or the construction of the contract is such that no fair or reasonable person would take or that the view of the arbitrator is not even a possible view.
Supreme Court of India Cites 27 - Cited by 166 - R Banumathi - Full Document

Sutlej Construction Limited vs Union Territory Of Chandigarh on 5 December, 2017

26. The Honourable Supreme Court in Sutlej Construction Ltd. v. UT of Chandigarh, (2018) 1 SCC 718, held that when the award is a reasoned one and the view taken is plausible, re-appreciation of evidence _______________ https://www.mhc.tn.gov.in/judis Page No. 22 of 29 Arb.O.P.(Comm.Div.) No.434 of 2023 is not allowed while dealing with the challenge to an award under Section 34 of the Arbitration And Conciliation Act, 1996 for setting aside an award. It further held that the proceedings challenging the award cannot be treated as a first appellate court against a decree passed by a trial court.
Supreme Court - Daily Orders Cites 5 - Cited by 110 - S K Kaul - Full Document

M/S.Sheladia Associates Inc vs Tamil Nadu Road Sector Project Ii on 30 April, 2019

27. The Honourable Supreme Court in Sheladia Associates Inc. V. TN Road Sector Project II, Represented by its Project Director, 2019 SCC OnLine Mad 17883 reminded itself of the Hodgkinson principle which has been explained by the Honourable Supreme Court in the oft- quoted and celebrated Associate Builders Case being Associate Builders V. Delhi Development Authority, (2015) 3 SCC 49. It held that Hodgkinson principle in simple terms means that the Arbitral Tribunal is the best judge with regard to quality and quantity of evidence before it. It further held that if there is no infraction of Section 28(3) of the Arbitration And Conciliation Act, 1996 the question of challenge on the grounds of public policy does not arise.
Madras High Court Cites 11 - Cited by 1 - M Sundar - Full Document
1   2 Next