Search Results Page

Search Results

1 - 10 of 14 (0.30 seconds)

Pravin Electricals Pvt. Ltd vs Galaxy Infra And Engineering Pvt. Ltd. on 8 March, 2021

In this regard, the decision of the Supreme Court in Praveen Electricals Pvt. Ltd. vs. Galaxy Infra and Engineering Pvt. Ltd. [(2021) 5 SCC 671], was relied on. For the proposition that merely because that the contract has come to an end by its termination due to breach, the arbitration clause does not get perished nor it is rendered inoperative.
Supreme Court of India Cites 45 - Cited by 36 - R F Nariman - Full Document

Damodar Valley Corporation vs K. K. Kar on 12 November, 1973

addressed by the Hon'ble Supreme Court in that decision in the context of Sections 62 and 39 of the Contract Act, 1872, was whether the arbitration clause incorporated in a contract perishes along with unilateral repudiation of the contract. The question for determination was: "where one of the parties refers a dispute or disputes to arbitration and the other party takes a plea that there was a final settlement of claims, is the court, on an application under Sections 9(b) and 33 of the Arbitration Act, 1940, entitled to enquire into the truth and validity of the averment as to whether there was or was not a final settlement on the ground that if that was proved, it would bar a reference to the arbitration inasmuch as the arbitration clause itself would perish." 5.2.1 As explained by the Hon'ble Supreme Court in Damodar Valley Corporation (supra), the questions of unilateral repudiation of the rights and obligations under the contract or of a full and final settlement of the contract are relatable to the performance or discharge of the contract, in which eventuality, much less the arbitration clause is put an end to, such questions fall within the purview of the arbitration clause.
Supreme Court of India Cites 5 - Cited by 131 - P J Reddy - Full Document

P.K. Ramaiah And Company vs Chairman & Managing Director, National ... on 1 October, 1993

(Para 7) 5.3 In State of Maharashtra vs. Navbharat Builders [1994 Supp (3) SCC 83], as well as in M/s. P.K. Ramaiah and Company vs. Chairman & Managing Director, National Thermal Power Corporation [1994 Supp (3) SCC 126], wherein a construction work contract, the contractor had accepted either by mutual agreement or voluntarily an unconditionally the payment in settlement of the contract claim, it was held that no arbitrable dispute survived and the contractor was not entitled to put forward the labour escalation or any subsequent claim was not an arbitrable dispute.
Supreme Court of India Cites 6 - Cited by 120 - Full Document

The Union Of India vs Kishorilal Gupta And Bros on 21 May, 1959

operates in respect of these purposes. It is to be observed that such is not the case in the present set of facts. 5.4 In the Union of India vs. Kishorilal Gupta [AIR 1959 SC 1362], respondents had entered into three contracts with the appellant, each of which had the arbitration clause. Before the contracts could be fully executed, disputes arose between the parties and allegations of breach was leveled. The parties thereafter entered into three fresh contracts on different successive dates settling the disputes on the terms contained in the new contract, wherein the respondents agreed to pay to the appellants certain monies in settlement of the dispute related to first two original contracts, and by last of the new agreement, the respondents agreed to pay to the appellant the specified amount preferable to third original contract.
Supreme Court of India Cites 7 - Cited by 202 - Full Document
1   2 Next