Search Results Page

Search Results

1 - 6 of 6 (0.19 seconds)

Associate Builders vs Delhi Development Authority on 25 November, 2014

22. When there were periodic certificates regarding the weather issued by the Kakinada port authority, there is no reason why a certificate issued by that authority regarding the strike was not produced by the Petitioners. Better still, the record of discharge of ships generally as maintained by the port authority for the relevant period could have been produced. The members of the AT, who belonged to the maritime trade, have appreciated the above evidence in light of their own experience of the industry practices. It could well be argued that another view on the same evidence is possible. But then that by itself does not attract any of the grounds under Section 34 of the Act to enable the Court to interfere. As has been reiterated in several decisions of the Supreme Court including Associate Builders v. Delhi Development Authority (supra) to warrant interference, the conclusions of the AT should be found to be perverse, irrational or contrary to the evidence on record or arrived at by overlooking the evidence. In the present case, it cannot be said that in allowing the claim of GESCL by the second impugned Award the AT ignored any relevant evidence, or failed to analyse the evidence on record or given OMP 498/2013 Page 14 of 15 reasons for the conclusions on such analysis. While the AT need not have again discussed the effect of the letter dated 16th May 1994 of the MoST, or the failure of the Petitioners to name an alternate port under Clause 24 of the C/P Agreement, since both those issues were already decided by the Court in its judgment dated 20th July 2011, the overall conclusion of the AT on whether the Petitioners were able to show that there was a strike between 23rd August and 17th September 1992 remains unaffected.
Supreme Court of India Cites 55 - Cited by 2182 - R F Nariman - Full Document

State Trading Corporation Of India Ltd vs M/S Toepfer International Asia Pte Ltd. on 2 July, 2014

17. Countering the above submissions, it was submitted by Mr. Sandeep Sethi, learned Senior counsel appearing for GESCL, that the scope of interference by this Court under Section 34 of the Act is extremely limited. Reliance was placed on the decision in State OMP 498/2013 Page 11 of 15 Trading Corporation of India Ltd. v. Toepfer International Asia PTE Ltd. 2014 (5) R.A.J. 301 (Del) to urge that "an error by the Arbitrator relatable to the interpretation of contract was an error within his jurisdiction and not an error on the face of the Award and was not amenable to correction by the Courts." It was pointed out that in the instant case, the three Arbitrators comprising the AT were persons of the same industry and after a detailed analysis of the evidence, had returned findings on facts. Therefore, the Award was not amenable to interference.
Delhi High Court Cites 15 - Cited by 86 - R S Endlaw - Full Document

Ascu Arch Timber Protection Ltd. vs Commissioner Of C. Ex., Calcutta on 7 April, 2004

20. The two pieces of evidence that were required to be considered were the certificate dated 23rd September 1994 issued by the KSAA and the letter dated 1st October 1994 from the office of the Labour Commissioner, Andhra Pradesh. The Court in its previous order felt that the AT had not considered the probative value of the above documents. The AT was obliged in terms of the law explained in ASCU Arch Timber Protection Ltd.(supra) to examine the above.
Supreme Court of India Cites 1 - Cited by 2 - Full Document
1