Search Results Page

Search Results

1 - 6 of 6 (0.36 seconds)

Punjab State Power Corporation Limited vs Punjab State Electricity Regulatory ... on 18 October, 2012

21. It is not in dispute that the tariff is always determined based on the capital cost, fixed cost and variable cost subject to prudent check by appropriate commission. This is very clear from Regulation 12 of the CERC Renewable Energy Regulations of 2012. This methodology has been adopted and applied by the State Commission in the impugned order. The Respondents placed reliance on Punjab Biomass case, wherein this Tribunal observed that the capital cost (fixed tariff) of the Biomass based Power Plant has to be determined based on plant to plant with reference to tariff applicable at the time of commissioning of the project as agreed under Implementation Agreement and not as per the tariff applicable during the actual date of commissioning of the plant. The summary of findings are as under:
Appellate Tribunal For Electricity Cites 20 - Cited by 11 - Full Document
1