Search Results Page

Search Results

1 - 6 of 6 (0.27 seconds)

M/S. Fair Air Engineers Pvt. Ltd.& Anr vs N.K.Modi on 20 August, 1996

12.         Section 3 of the Act, is worded in widest terms, and leaves no manner of doubt, that the provisions of the Act, shall be, in addition to, and not in derogation of any other law, for the time being, in force. The mere existence of Arbitration Clause No.53, in the document, aforesaid, would not oust the Jurisdiction of the Consumer Fora, in view of the provisions of Section 3 of the Act. Similar principle of law, was laid down, in Fair Engg. Pvt. Ltd. & another Vs N.K.Modi (1996) 6 SCC 385= III (1996) CPJ 1 (SC) and C.C.I. Chambers Coop. Housing Society Ltd. Vs Development Credit Bank Ltd. (2003) 7 SCC 233= III (2003) CPJ 9 (SC). In this view of the matter, the submission of the Counsel for the Opposite Party, being devoid of merit, must fail, and the same stands rejected.
Supreme Court of India Cites 39 - Cited by 802 - K Ramaswamy - Full Document

Cci Chambers Co-Op. Hsg. Society Ltd vs Development Credit Bank Ltd on 29 August, 2003

17.   No doubt, a period of two years, could be extended due to force majeure circumstances. It was for the Opposite Party, to clearly explain, in the written reply, as to what were those circumstances, which were beyond its control, as a result whereof, the construction of the showrooms, could not be completed, in time, and possession could not be delivered by 28.02.2008. In the written reply, the only plea taken up by the Opposite Party, was to the effect, that other buyers, like the complainants, of the showrooms, in the same project, did not make the payment of installments, in time, as a result whereof, there was delay in the completion of project. No evidence, in this regard was, however, produced by the Opposite Party. It may be stated here, that the complainants, in this case, have already deposited a huge amount of Rs.41,24,931/-, referred to above, towards the part price of showroom. When the complainants found that there was no progress, in the construction of project, at the site, it was not obligatory upon them, to pay the remaining installments, until a firm assurance had been held out to them, that the project would be completed, in the very near future. As stated above, till date, the project has not been completed, nor possession of the showroom has been delivered to the complainants. Since, the Opposite Party failed to adhere to the terms and conditions, for the allotment of commercial showrooms, in the said project, it could not blame the complainants, for not making the payment of remaining sale consideration/ installments. Since, the construction was not being undertaken, as per schedule, if the complainants did not pay the remaining installments, they could not be held responsible for delay, in the completion of project. The Opposite Party, therefore, failed to prove any circumstance, beyond its control, due to which the construction was delayed.
Supreme Court of India Cites 8 - Cited by 497 - R C Lahoti - Full Document
1