Search Results Page

Search Results

1 - 10 of 29 (0.25 seconds)

Secretary, Thirumurugan Co-Operative vs M. Lalitha (Dead) Through Lrs. & Ors on 11 December, 2003

"We are unable to persuade ourselves to agree with the Learned Counsel.  In our opinion, the decision of the State Commission being based on the authoritative pronouncements by the Hon'ble Supreme Court and also on the decision dated 02.05.2016, rendered by this Bench in the case of  Lt. Col. Anil Raj & Ors. Vs.  M/s Unitech Limited & Ors. in CC No. 346/2013, in which we have held that notwithstanding the amendments in the Arbitration Act, the reasoning and ratio of the decision of the Hon'ble Supreme Court, in the case of  Secretary, Thirumurugan Cooperative Agricultural Credit Society Vs.  M. Lalitha (Dead) Through LRs.
Supreme Court of India Cites 30 - Cited by 561 - S V Patil - Full Document

Dlf Universal Ltd. vs Nirmala Devi Gupta on 15 February, 2016

Similar view was reiterated by the National Commission, in DLF Universal Limited Vs Nirmala Devi Gupta,  2016 (2) CPJ 316. The principle of law, laid down, in the aforesaid cases, is fully applicable to the present case. The  complainant, thus, falls within the definition of a 'consumer', as defined under Section 2(1)(d) of the Act. Such an objection, taken by  the Opposite Parties, in their written reply, therefore, being devoid of merit, is rejected.
Supreme Court - Daily Orders Cites 0 - Cited by 467 - Full Document

Shri Rajeev Nohwar & Anr., vs M/S Sahajanand Hi Tech Construction ... on 6 May, 2016

Even otherwise, the Opposite Parties cannot evade their liability, merely by saying that since the word endeavour/tentative/ proposed was mentioned in the Agreement, for delivery of possession of the unit, as such, time is not to be considered as essence of the contract. Non-mentioning of exact date of delivery of possession of the unit(s) in the Buyer's Agreement, is an unfair trade practice, on the part of the Builder. The builder is bound to mention the exact/specific date of delivery of possession of the unit(s) to the allottees/purchasers thereof.  It was so said by the Hon`ble National Commission, in Rajeev Nohwar & Anr. V/S Sahajanand Hi Tech Construction Pvt Ltd, 2016 (2) CPR 769. Relevant portion of the said case reads thus:-
National Consumer Disputes Redressal Cites 18 - Cited by 107 - Full Document

Mr. Prabhujeev Singh Bajaj vs Emaar Mgf Land Ltd. on 29 June, 2016

A bare perusal of the intimation of possession letter dated 09.08.2016 (Annexure C-7) clearly reveals that it is not a proper possession letter, rather it is just an intimation regarding possession because it is clearly stated in the said letter that " We are pleased to inform you that this process of handing over of the plots in Sector 109, Mohali Hills shall commence within 60 days of this letter x x". It means that it is not a proper possession letter and just a paper possession because in the said letter, it has been clearly stated that process of handing over of possession shall start within 60 days of the said letter. Even the Opposite Parties failed to place on record any document, which could prove that all the basic amenities were completed at the site. Not only this, it is also relevant to note that a number of cases of Sector 109 of Emaar MGF Land Limited have already been decided by this Commission regarding the issue of sealing of project by Forest Department and other issues in Sector 109, one of which is titled as " Prabhujeev Singh Bajaj Vs. Emaar MGF Land Limited & Anr., Complaint Case No.43 of 2016, decided by this Commission vide order dated 29.06.2016", the relevant portion of the said judgment reads thus :-.
State Consumer Disputes Redressal Commission Cites 26 - Cited by 22 - Full Document

Emaar Mgf Land Pvt. Ltd. vs Krishan Chander Chandna on 29 September, 2014

"31. However, the main grouse of the complainant is that, despite relocation to the said units, even then, actual physical possession thereof, was not offered to him, whereas, on the other hand, paper offer was made to him, vide letters dated 25.08.2014 and 07.11.2014, because when he visited the site after receiving the said letters, to see development and basic amenities, the same were found missing and besides  that, all entry points of the project, had been sealed by the Forest Department, as opposite parties no.1 and 2, failed to take requisite permissions/sanction from it. Thus, in these circumstances, the principal question, which goes to the root of the case, and falls for consideration, is, as to whether, offer of possession made by opposite parties no.1 and 2, to the complainant, vide letters dated 25.08.2014 and 07.11.2014, in respect of the relocated units, could be said to be genuine offer or not. It is well settled law that the onus to prove that the project had been completed and the area/site, in question, is fully developed is on the builder/opposite parties no.1 and 2. It was so said by the National Commission, in  Emaar MGF Land Limited and another Vs. Krishan Chander Chandna, First Appeal No.873 of 2013 decided on 29.09.2014. It is very strange that not even an iota of evidence has been placed, on record, by opposite parties no.1 and 2, to prove that when offer was made to the complainant, in respect of the units, in question, development work was complete and that all the basic amenities were in existence. On the other hand, in case, all the development activities, had been undertaken, and completed at the site, by the said dates, then it was for opposite parties no.1 and 2, which could be said to be in possession of the best evidence, to produce cogent and convincing documentary evidence, in the shape of the reports and affidavits of the Engineers/Architects, as they could be said to be the best persons, to testify, as to whether, all these development activities, had been undertaken and completed at the site or not, but they failed to do so. Opposite parties no.1 and 2 were also required to produce on record, a copy of the Completion Certificate (if obtained), having been issued by the Competent Authority, which could be said to be best evidence, to prove their case, but they miserably failed to do so. It is well settled law that before offering/delivery of possession of unit, in a project, it is mandatory to obtain completion certificate, from the Competent Authority(s), failing which the purchaser is at liberty to say no, to such an offer.
National Consumer Disputes Redressal Cites 6 - Cited by 167 - Full Document
1   2 3 Next