Search Results Page

Search Results

1 - 9 of 9 (0.28 seconds)

Hindustan Construction Company Ltd vs Nhpc Ltd on 4 March, 2020

36. It was conceded on behalf of the respondent that the petitioner is continuing to work on the site even after April, 2022 and no express letter indicating termination of Contract has been served upon the petitioner. An ambivalent situation prevails wherein the respondent though has served Notice of Correction and the Delay Damages Notice, but has yet not served any Notice of termination or has notified the petitioner to stop the work at site after April, 2022. Therefore, as held in the cases of Hindustan Construction Limited (supra) that though invocation of Bank Guarantee cannot be prohibited or injuncted, it is held to be a fit case where the Signature Not Verified Digitally Signed By:NIRMLA TIWARI O.M.P. (I) (COMM.) 208/2022 Page 16 of 17 Signing Date:05.07.2022 14:24:17 respondent is directed to give a prior Notice of 15 days expressing his intention to revoke the Bank Guarantee before revocation of Bank Guarantees.
Supreme Court of India Cites 8 - Cited by 39 - R F Nariman - Full Document

U.P. State Sugar Corporation vs M/S. Sumac International Ltd on 4 December, 1996

31. It needs to be further examined whether petitioner is entitled to injunction against invocation of Performance Guarantees. The law in regard to injunctions for restraining invocation/ revocation of bank guarantee has been clearly laid down by the Apex Court in U.P. State Sugar Corporation vs. Surmac International Ltd. (1997) 1 SCC 568 wherein the principle was clearly enunciated that on the enforcement of a Bank Guarantee or a Letter of Credit in respect of Bank Guarantee which is sought to be encashed by a Signature Not Verified Digitally Signed By:NIRMLA TIWARI O.M.P. (I) (COMM.) 208/2022 Page 14 of 17 Signing Date:05.07.2022 14:24:17 beneficiary, the bank giving such guarantee is bound to honour it as per its terms irrespective of any dispute raised by its customer. It was held that the existence of any dispute between the parties to the Contract is not a ground to restrain the enforcement of Bank Guarantees. The only two exceptions recognized for grant of order of injunction are:
Supreme Court of India Cites 11 - Cited by 385 - S V Manohar - Full Document

Manohar Lal Sharma vs Narendra Damodardas Modi on 10 April, 2019

In the decision of Manohar Lal Sharma Vs. Narendra Damodar Dass Modi (2019) 3 SCC 25, the Apex Court highlighted the significance of the contracts pertaining to Defence Services and observed that adequate military strength and capability to Signature Not Verified Digitally Signed By:NIRMLA TIWARI O.M.P. (I) (COMM.) 208/2022 Page 11 of 17 Signing Date:05.07.2022 14:24:17 discourage and withstand external aggression and to protect the sovereignty and integrity of India is a matter of utmost concern for the Nation. The empowerment of defence forces with adequate technology and material support is, therefore, a matter of vital importance. The parameters of judicial review of administrative decisions with regard to Award of Tenders and Contracts are confined to the scrutiny of the decision making process on the parameters of unreasonableness and malafide. The Court should not exercise its power of judicial review even if a procedural error is committed to the prejudice of the Tenderer since private interests cannot be protected while exercising such judicial review.
Supreme Court of India Cites 42 - Cited by 42 - R Gogoi - Full Document

Himadri Chemicals Industries Ltd vs Coal Tar Refining Company on 7 August, 2007

33. The Apex Court in Himadri Chemicals Industries Ltd. vs. Coal Tar Refining Company (2007) 8 SCC 2010 made a reference to the aforementioned judgment and concluded that since the Bank Guarantee or a Letter of Credit is an independent and a separate contract and is absolute in nature, existence of any dispute between the parties to the contract would not be a ground for issuing an order of injunction to restrain enforcement of bank guarantee.
Supreme Court of India Cites 4 - Cited by 256 - T Chatterjee - Full Document

Reliance Airport Developers Pvt. Ltd vs Airports Authority Of India And Ors on 7 November, 2006

In Reliance Airport Developers Pvt. Ltd. vs. Airport Authority of India (2006) 10 SCC 1 it was noted that certain areas of governmental activity, national security being the paradigm, the courts have regarded themselves as incompetent to investigate, beyond an initial decision as to whether the government‟s claim is bonafide. In this kind of non-justifiable area, judicial review is not entirely excluded, but is very limited.
Supreme Court of India Cites 23 - Cited by 96 - A Pasayat - Full Document

Hind Construction Contractors By Its ... vs State Of Maharashtra on 30 January, 1979

28. This aspect was considered in detail by the Apex Court in its decision in M/s Hind Contractors Vs. State of Maharashtra (1979) 2 SCC 70, and it was held that whether the time is the essence of the Contract would essentially be a question of the intention of the parties to be gathered from the terms of the Contract. Even when the parties have expressly provided that Time is the essence of the Contract, such stipulation would have be read along with the other provisions of the Contract and on construction and interpretation of the terms of the Contract, inference that completion of the work by a particular date was intended to be fundamental, may be excluded. For instance, if the Contract includes clauses providing extension of time in certain contingencies or for payment of fine or penalty for every day or week, the work undertaken remains unfinished on the expiry of the time provided in the contract, such clauses would be construed as rendering ineffective the express provision relating to the time being the essence of the Contract.
Supreme Court of India Cites 0 - Cited by 94 - V D Tulzapurkar - Full Document

M/S Nhpc Ltd. vs M/S Hindustan Construction Company ... on 4 December, 2020

35. Similar facts as in the present case came up for consideration in Signature Not Verified Digitally Signed By:NIRMLA TIWARI O.M.P. (I) (COMM.) 208/2022 Page 15 of 17 Signing Date:05.07.2022 14:24:17 Hindustan Construction Company Ltd. vs. NHPC Ltd. O.M.P. 536 of 2014 decided by this Court on 30th May, 2014; Hindustan Construction Company Ltd. vs. NHPC Ltd. O.M.P. 536 of 2014 decided by this Court on 12th February, 2015; NHPC Ltd. vs. Hindustan Construction Company Ltd. FAO (OS) 131 of 2015 decided by the Division Bench of this Court on 28th May, 2015, wherein it was held consistently that where the bank guarantee has not yet been invoked by the respondent, the directions for prior Notice of certain days before invocation is not violative of the settled law prohibiting any injunction against revocation of bank guarantee. In these cases, it was categorically observed that the factum of notice of invocation of bank guarantee can be of no prejudice to the petitioner, since after giving such notice, it will be open to the respondent to proceed to invoke the bank guarantee subject to the petitioner seeking appropriate remedies. By providing for prior Notice, the respondent was not being injuncted from invoking the Bank Guarantee but merely some time was granted to the petitioner to seek its remedies in case the respondent sought to encash it. CONCLUSION
Delhi High Court Cites 8 - Cited by 1 - R Palli - Full Document
1