Maharashtra State Power Generation Co. ... vs Maharastra Electricity Regulatory ... on 10 April, 2008

Accordingly, the State Commission is directed to re-determine the IDC for the actual period of commissioning of the project on the principles of pari passu deployment of equity and debt and then work out the excess IDC for the period of time overrun on a pro rata basis with respect to actual time taken in completion of the project and limit disallowance to 50% of the same from the total IDC. The principles laid down by us for IDC will also be applicable to the amount of AG&SP loan subsidy.