Search Results Page

Search Results

1 - 7 of 7 (0.29 seconds)

Sanshin Chemicals Industry vs Orientals Carbons And Chemicals Ltd. ... on 16 February, 2001

7. Chapter 7 of the Arbitration and Conciliation Act, 1996 provides for a recourse against arbitration award by way of an application which can be made by either parties u/s 34 of the Act. The statute provides that on an application of either parties, an arbitration award including an interim award can be challenged and set aside. Reliance placed on AIR 2001 SC 1219 Sanshin Chemical Industry Vs. Oriental Carbon & Chemicals. However, the Hon'ble Apex Court in catena of judgment has always held that section 34 does not provide for an appeal against the arbitration award but provides for a limited remedy to the court whereby which the court can review and set aside the arbitral award only on the ground specified under sub­section (2) and sub­section (3) of the Act. It has been held in (2000) 3 Arb.
Supreme Court of India Cites 13 - Cited by 15 - Full Document

Laxmi Mathur vs The Chief General Manager, Mtnl, Mumbai on 17 April, 2000

LR 684 (Bombay) titled Laxmi Mathur Vs. CGM MTNL that erstwhile Arbitration CS No.192/11/05 MTNL Vs. Vaishali Enterprises 8/15 9 Act, 1940 provides for a wider scope against an Arbitration Award, but a remedy against section 34 of the Arbitration award under the 1996 Act, is available on limited grounds as provided in the statute itself. It is further a settled preposition of law that challenge to arbitral award is not to the decision but limited only to the decision making process.
Bombay High Court Cites 5 - Cited by 45 - V C Daga - Full Document

Rajasthan State Mines & Minerals ... vs Eastern Engineering Enterprises & Anr on 20 September, 1999

Ld. Counsel for petitioner has further relied upon the pronouncement of law laid down in 1991 (9) SCC 283 titled Rajasthan State Mines and Minerals Ltd. Vs. Eastern Engineering Enterprises thereby stating that if the arbitrator ignore the specific terms and conditions of the contract, it is the question of jurisdictional error which could be corrected by the Court in exercise of its power u/s 34 of the Act,. Though, there is no dispute about the preposition of law in the aforesaid judgment that Ld. Arbitrator is strictly bound by terms and conditions as stipulated in the original agreement, and being a creature of the agreement can not go beyond the terms of the agreement or reference, he has to answer, it may however be seen that main question before this court is that once the agreement has expired the work undertaken during the extended period by the respondent was not governed by the terms and conditions of the original contract. This arguments of the petitioner is fallacious without any basis and contrary to the records.
Supreme Court of India Cites 20 - Cited by 335 - Full Document

Union Of India (Uoi) vs Hakam Chand & Co. on 29 August, 2002

Reliance placed on 2002 (65) DRJ 400 titled Union of India Vs. Hakam Chand & Co. Thus, this court cannot and should not sit over a evaluation arrived by the Ld. CS No.192/11/05 MTNL Vs. Vaishali Enterprises 14/15 15 Arbitrator unless the award suffer from bias, incapacity, non­ representation and any such irregularity or the arbitrator has failed to follow the Principles of Natural Justice. This court finds no such irregularity or illegality in the arbitral process carried out by Ld. Arbitrator in arriving on his findings of the award dated 01.03.2005. Resultantly, the petitioner has failed to make out a case calling for an interference for setting aside the award dated 01.03.2005 in exercise of this court's power u/s 34 of the Act. The objection petition is accordingly dismissed. Arbitration record be sent back to Ld. Arbitrator with the copy of this order. Records of this court be consigned to Record Room after due completion.
Delhi High Court Cites 14 - Cited by 28 - R C Chopra - Full Document

Golkonda Engg. Enterprises Limited vs Mahanagar Telephone Nigam Limited on 6 April, 2005

1. By way of present judgment, I shall conscientiously adjudicate upon the petition under Section 34 of the Arbitration and Conciliation Act, 1996 for setting aside the arbitral award dated 01/03/2005 (hereinafter called the CS No.192/11/05 MTNL Vs. Vaishali Enterprises 1/15 2 "impugned Award") as passed by Shri A.K. Nagar, Sole Arbitrator, Chief Engineer (C) CTO Project, Bharat Sanchar Nigam Ltd., in case No. ARB/AKN/24/2004 titled M/s Vaishali Enterprises Vs. Mahanagar Telephone Nigam Ltd.
Andhra HC (Pre-Telangana) Cites 8 - Cited by 1 - N V Ramana - Full Document
1