1 - 2 of 2 (0.21 seconds)State Of Kerala And Ors. vs T.N. Anil on 21 December, 2001
Petitioner has entered into Ext. P1 agreement for
upgradation of a road. According to the petitioner, the
project was being financed by world bank and therefore,
there is no difficulty for payment to be effected. According
to the petitioner, other contractors doing similar
works are paid, overlooking petitioner's priority and against
the principle of 'first done first paid' as held by this Court in
State of Kerala v. Anil [2002 (1) KLT 371 (FB)]. During
the course of the work, a part bill was raised by the
petitioner and according to the petitioner, the certified bill
alone will come to Rs. 68 Crores and respondents are duty
bound to release the bill amount to the petitioner. It is in
this background seeking appropriate directions, this writ
petition is filed.