Bses Yamuna Power Limited vs Central Electricity Regulatory ... on 24 March, 2015

"15.3 This Tribunal has relied on the judgment of Hon'ble Supreme Court in the case of West Bengal Electricity Regulatory commission Vs CESC Limited while passing the judgment in Appeal No.55 of 2013 dated 24.3.2015. The relevant part of this Tribunal's judgment in Appeal No.55 of 2013 dated 24.3.2015 in the case of BSES Yamuna Power Ltd., vs. Central Electricity Regulatory Commission (CERC), is as under: "18.6. We have gone through the proposition of law settled by the Hon'ble Supreme Court of India in West Bengal Electricity Regulatory Commission Vs.CESC Limited (2002) 8 SCC 715 in which the Hon'ble Apex Court had observed that the employees cost prudently incurred needs to be reimbursed to the Utility.
Appellate Tribunal For Electricity Cites 19 - Cited by 2 - Full Document