under an approved
framework of mining plan, which should provide for reclamation and
rehabilitation of mined out areas. Mining Plan should take note ... compliance.
(4) Mine working shall be strictly as per the conditions of approved
mining plan /simplified mining scheme / scheme of mining, as the
case
consists of 136 mining leases comprising of total mining area of
281 hectares.
5. The petitioner, like all other mine owners, exists and
functions ... that vide letter dated 13.07.2017, the Assistant Mining Engineer,
Rishabhdev informed the Additional Director (Mines) that 76
mining lease holders have submitted proposal for extension
consists of 136 mining leases comprising of total mining area of
281 hectares.
5. The petitioner, like all other mine owners, exists and
functions ... that vide letter dated 13.07.2017, the Assistant Mining Engineer,
Rishabhdev informed the Additional Director (Mines) that 76
mining lease holders have submitted proposal for extension
consists of 136 mining leases comprising of total mining area of
281 hectares.
5. The petitioner, like all other mine owners, exists and
functions ... that vide letter dated 13.07.2017, the Assistant Mining Engineer,
Rishabhdev informed the Additional Director (Mines) that 76
mining lease holders have submitted proposal for extension
consists of 136 mining leases comprising of total mining area of
281 hectares.
5. The petitioner, like all other mine owners, exists and
functions ... that vide letter dated 13.07.2017, the Assistant Mining Engineer,
Rishabhdev informed the Additional Director (Mines) that 76
mining lease holders have submitted proposal for extension
consists of 136 mining leases comprising of total mining area of
281 hectares.
5. The petitioner, like all other mine owners, exists and
functions ... that vide letter dated 13.07.2017, the Assistant Mining Engineer,
Rishabhdev informed the Additional Director (Mines) that 76
mining lease holders have submitted proposal for extension
consists of 136 mining leases comprising of total mining area of
281 hectares.
5. The petitioner, like all other mine owners, exists and
functions ... that vide letter dated 13.07.2017, the Assistant Mining Engineer,
Rishabhdev informed the Additional Director (Mines) that 76
mining lease holders have submitted proposal for extension
consists of 136 mining leases comprising of total mining area of
281 hectares.
5. The petitioner, like all other mine owners, exists and
functions ... that vide letter dated 13.07.2017, the Assistant Mining Engineer,
Rishabhdev informed the Additional Director (Mines) that 76
mining lease holders have submitted proposal for extension
consists of 136 mining leases
comprising of total mining area of 281 hectares.
5. The petitioner, like all other mine
owners, exists and functions ... that vide letter dated 13.07.2017,
the Assistant Mining Engineer, Rishabhdev
informed the Additional Director (Mines) that 76
mining lease holders have submitted proposal for
extension
consists of 136 mining leases comprising of total mining area of
281 hectares.
5. The petitioner, like all other mine owners, exists and
functions ... that vide letter dated 13.07.2017, the Assistant Mining Engineer,
Rishabhdev informed the Additional Director (Mines) that 76
mining lease holders have submitted proposal for extension