Road, Chennai-10. In the said area the
Chennai Metro Rail Limited (CMRL) Phase-II, corridor-III is being
constructed.
2. The applicant has alleged ... above grounds, a direction is sought for to the CMRL and the
2nd respondent, Tata Project Limited, to stop forthwith all the
construction activity
Road, Chennai-10. In the said area the
Chennai Metro Rail Limited (CMRL) Phase-II, corridor-III is being
constructed.
2. The applicant has alleged ... above grounds, a direction is sought for to the CMRL and the
2nd respondent, Tata Project Limited, to stop forthwith all the
construction activity
Road, Chennai-10. In the said area the
Chennai Metro Rail Limited (CMRL) Phase-II, corridor-III is being
constructed.
2. The applicant has alleged ... above grounds, a direction is sought for to the CMRL and the
2nd respondent, Tata Project Limited, to stop forthwith all the
construction activity
remediation
system was connected to the local power grid.
In 2017, CMRL started construction activity (Excavation of soil &
Extraction of groundwater) for the construction ... used for remediation. In October
2018, after many months of negotiation with CMRL, BPCL/Stratuswas
able to relocate the SVE unit and restart
month.
iv) The proposed metro excavation work by M/s.CMRL is going to
impact the existing SVE system including some of the monitoring ... operate the SVE system till the time of
commencement of M/s.CMRL work.
b) The SVE system may be operated round the clock against
Chairman, TNPCB;
CMD, M/s Chennai Metro Rail Corporation Ltd., (M/s.
CMRL) and CMD, M/s. harat Petroleum Corporation Ltd
(M/s. BPCL ... chairmanship of
Chairman, CPC B on 0l.03.2019 - upon completion of
CMRL soil excavation works, IWs BPCL to submit a
Detailed Project Report
Tondiarpet, Chennai;
M/s BPCL submitted the Detailed Site Assessment Report
(Post CMRL Excavation) on 06.08.2021, the summary of the assessments
are as below ... feet) were installed to compensate the wells abandoned
due to CMRL Excavation, all these wells were monitored once in a month,
the reductionof contamination
said meeting has been attended by all stake holders
including officials from CMRL, CPC B and BPCL and representations of the
applicant.
The four topics ... remediation process. It appears
that there was already discussion between BPCL and CMRL and
they have permitted the BPCL to proceed with the activity except
stake holders including Bharat Petroleum Corporation Ltd.,
(BPCL) Chennai Metro Rail Ltd. (CMRL) and others on 19.01.2017 at 3.00
pm. After discussion it was decided ... have a separate meeting between
CMRL and BPCL for finalising the place for permission to be granted for
CMRL to enable BPCL to carry
Chennai - 600 003.
5) Managing Director
Chennai Metro Rail Limited,
Admin Buildings, CMRL Depot,
Poonamallee High Road,
Koyambedu, Chennai 600 107.
... Respondent(s)
For Applicant ... clean water body by removal of construction debris
dumped by CMRL, respondent No.5 and pollutants discharged by
Respondent No.3.
2. It was alleged