subject to compliance of many conditions, most of which were incomplete. Completion certificate was not available. To say so, reliance was placed upon information received ... opposite party to handover possession to the complainant complete in all respects after obtaining completion certificate but it miserably failed to do so. The case
powers to give permission for development of such immovable property; (q) "completion certificate" means the completion certificate, or such other certificate, by whatever name called
approvals taken and the approvals which are pending subsequent to commencement certificate; (e) quarterly up-to-date status of the project; and (f) such other ... allottees are executed. (b) be responsible to obtain the completion certificate or the occupancy certificate, or both, as applicable, from the relevant competent authority
date of commencement of this Act and for which the completion certificate has not been issued, the promoter shall make an application to the Authority ... from registration under this Act; (b) where the promoter has received completion certificate for a real estate project prior to commencement of this
allow persons to enter into possession until a completion certificate where such certificate is required to be given under any law, is duly given ... person shall take possession of a flat until such completion certificate has been duly given by the local authority);
j ..
k make a full
take all the requisite permissions from the competent authorities such as completion certificate, environment clearance, electricity connection, NOC from forest department, approval of layout plan ... Government had not approved the layout plan nor issued the completion certificate to show that plots are ready for possession.
2. It was further stated
Mumbai. On 22 nd June,
2007, the defendant no.1 obtained completion certificate for Wing 'A' which was
subsequently registered as Snow Flama ... completed much prior to the introduction of Regulation
33(24) of the Development Control Regulation. The completion certificate was
already granted by the Municipal Corporation
Financial Year 2006-07
and completed the same in the month of March 2012 and completion
certificate from Pune Municipal Corporation was obtained ... section 80-IB(10) , date of completion of construction shall be taken to
be date on which completion certificate in respect of the housing
project
Society, original Deed of Conveyance, property card, original IOD, Commencement Certificate, Occupancy Certificate, Building Completion Certificate, Draft Plan, along with all other necessary documents ... sanction plan, copy of the Completion Certificate, Commencement Certificate, Copy of the amended Plan, Occupancy Certificate, Certificate issued by the Chief Fire Officer
Mumbai. On 22 nd June,
2007, the defendant no.1 obtained completion certificate for Wing 'A' which was
subsequently registered as Snow Flama ... completed much prior to the introduction of Regulation
33(24) of the Development Control Regulation. The completion certificate was
already granted by the Municipal Corporation