mentioned that "No completion certificate acquired
however buildings are complete and occupied. Architect have issued the
completion certificate". He accordingly submitted that ... table:
Project Architect Certificate Application for Completion
Commencement Completion Completion Certificate /
date date Certificate / Occupancy
Occupancy Certificate
Certificate to date
Collector, Pune
mentioned that "No completion certificate acquired
however buildings are complete and occupied. Architect have issued the
completion certificate". He accordingly submitted that ... table:
Project Architect Certificate Application for Completion
Commencement Completion Completion Certificate /
date date Certificate / Occupancy
Occupancy Certificate
Certificate to date
Collector, Pune
applied for completion
certificate at the strength of the Architect Certificate
appearing on page 16 of the Paper Book-I, and completion
certificate was issued ... competent to issue
completion certificate. According to learned Assessing Officer the
Local Authority to issue completion Certificate was the Collector
Pune. Thirdly on the ground
noted that the
project was completed during assessment year 2003-04 and had received the
completion certificate from Pune Municipal Corporation. Part completion
certificate ... assessee received
final completion certificate on 20.03.2003. As per final completion certificate, the
same was issued with reference to building commencement certificate No.1032,
dated
1512/PN/2014
applied for the first completion certificate on 16-08-2010. The First
Completion Certificate No.OOC/0512110 dated 11th October ... occupancy certificate along with
the Completion Certificate issued by the architect in prescribed form.
After the receipt of application the occupancy/completion Certificate is
either
Pune, and therefore it was M/s R.K.Chavan Infrastructure Pvt. Ltd.,
Pune, which was entitled to the certificate of successful completion
of work ... Pune and therefore it was M/s R.K.Chavan Infrastructure
Pvt. Ltd., Pune which was entitled to the certificate of successful
completion of work
Completion Certificate for the entire project. We
are submitting herewith the application for Completion Certificate dated 22-
01-2004vide Commencement Certificate No.1372 dated ... architect's certificate confirming completion
of construction of building, the assessee applied for the completion certificate
to the Pune Municipal Corporation
completion basis. The completion
certificate for the project has been obtained in piece-mill for the part of the
project. However, the completion certificate ... applied for Completion Certificate for the entire project. We are
submitting herewith the application for Completion Certificate dated 22-01-
2004vide Commencement Certificate No.1372 dated
noted that certain details were filed
including the copies of commencement certificate , completion certificate
and sale agreement but there was no proof either ... Pune Municipal Corporation
and completion was granted vide letter No.DPO/SEC 6/0231/07/203 dated
31.3.2008. However, the Pune Municipal Corporation granted completion
Municipal Corporation (PMC) for issue of Completion Certificate on
29.03.2008. However, the PMC had not issued Completion Certificate to the
assessee and that was only ... completion certificate. The assessee admittedly, had completed the construction of
the project before the stipulated date and had applied for issue of completion
certificate