Status
1. EUP 03 2 Under construction
2. VUP 02 De-scoping proposed
3. Minor Bridge 06 3Under construction
4
4. Fly over 01 De ... construction of Railway over bridge. In respect of Package No. IV, De-scoping of
work in the stretch of km 243.00 to km 248.500 falling
under construction; in respect of 02 VUP, De-scoping has been proposed
and further, in respect of one flyover also, De-scoping has been proposed ... Ajay Kumar Sinha and Col. Kapoor have
apprised the Court that De-scoping work relates to the stretch of NH-33 passing the
Steel City
contract.
B, Intumescent Paint:
Intumescent painting (interior and exterior) would be de-scoped from the
scope of work allotted to VB in the Contract ... terms of the contract.
C. Lift:
a. Lift to be de-scoped ftom the scope of work allotted to VB in the
Contract
constructed but the same could not materialize. Therefore, it had de-scoped the construction of service road from the agreement of the concessionaire ... apprising him of the decision of N.H.A.I. to de-scope the work relating to construction of service road has also been placed
place. Finally, the six laning of
Dhanua portion had to be de-scoped from the contract owing to
delay in obtaining forest and wildlife clearance ... should have taken prudent action and would have advised NHAI
for de-scoping of the forest affected stretch to avoid prolongation
cost such as idling
value of Rs.10,40,00,000/- were agreed to be de-scoped and this
agreement was also confirmed through amendments. This fact ... that Leighton had not carried out such works that were already de-scoped.
17. Learned Senior Counsel submitted that it was clear that the second
returned the same on 11.08.2022,
requesting revision in light of the de-scoping of the Brahmani
Bridge amounting to Rs. 57.74 Crores, as per Competent ... point that when SPS-16 was submitted the issue of de-
scoping of a major bridge over Brahmani River at Km
401.250 was simultaneously being
final bill, and
amounts towards loss of profit for de-scoping of
certain works?
6. Whether the occupation of the building by
the respondent would ... done and not for unpaid bills or loss of profit on de-scoping of the
work.
10. On issue No.7 which related to acceptance
present, learned counsel for writ petitioners de-scopes the prayer in the
Page 4 of 9
WP and he submits that it would suffice ... hearing, more particularly owing to learned counsel for writ petitioners de-
scoping the prayer, we deem it appropriate to make a simple order directing
respondent
without prejudice to Prayer (d) above,
direct the Respondents to de-scope the residual works
(approximately 3-4%) from the original contractual scope under
Article ... Completion
Certificate and release all outstanding payments inclusive of the
de-scoped works to the Petitioner;
h) Issue a Writ of Mandamus or any other