scope of work without amending the schedule of
rates.
21. It is submitted that the project as awarded to the plaintiff was de-
scoped ... de-scoped project was given at the risk and expense of the
plaintiff to another third party entity.
22. It is submitted that despite urgency
without prejudice to Prayer (d) above,
direct the Respondents to de-scope the residual works
(approximately 3-4%) from the original contractual scope under
Article ... Completion
Certificate and release all outstanding payments inclusive of the
de-scoped works to the Petitioner;
h) Issue a Writ of Mandamus or any other
date of this Order. For hindered items, the
Claimant shall pursue de-scoping applications with the Respondent.
(g) Non-compliance of any one or more
however, as found by the learned Arbitrator, only
58% of the de-scoped work was completed by the respondents as
on 01.09.2020, clearly evidencing that
take recourse to
appropriate proceedings, including a suit challenging the de-scoping and all
consequences that flow therefrom.
2. Suit along with pending applications
work, was
not handed over to the petitioner, his client would de-scope "the
work", so as to delete, from the work originally