RAB1 to RAB13 pg 19 vol xvii
De scoped Value: 37005000=00
Balance Value on 25.10.11:40630493.00, 40%=16252197.00
The claim of 40% hike ... de-scoped work withdrawn from VPSPL on 25th
October 2011 was Rs. 3,70,05,000/-. Since the total Contract Value
amount paid/being paid by the Respondent-Corporation
on account of de-scoping of work;
Counter-Claim No.2: And/or in the alternative ... Award of Rs.7.93
crores granted to the Appellant for de-scoped work in the Cuttack City
pipeline project. The Respondent argued that this
amount paid/being paid by the Respondent-Corporation
on account of de-scoping of work;
Counter-Claim No.2: And/or in the alternative ... Award of Rs.7.93
crores granted to the Appellant for de-scoped work in the Cuttack City
pipeline project. The Respondent argued that this
account of the over-head costs of handing over de-scoped work
to the new contractor;
(viii) On 24.08.2020, the Respondents were intimated ... also reduce the
scope of work. And accordingly, because you have
failed to resolve our grievances, partial scope of work
was de-scoped
amount paid/
being paid by the Respondent-Corporation on
account of de-scoping of work;
Counter-claim No.2: And/or in the alternative ... Respondent a sum
of Rs. 7.93 Crores in respect of the de-scoped
work It shall carry simple interest @ 12%
from 01.01.2016 onwards till
amount paid/
being paid by the Respondent-Corporation on
account of de-scoping of work;
Counter-claim No.2: And/or in the alternative ... Respondent a sum
of Rs. 7.93 Crores in respect of the de-scoped
work It shall carry simple interest @ 12%
from 01.01.2016 onwards till
EPCM-21 & 22 CONTRACTS_CONFIRMATION
REQUIRED W.R.T THE DE-SCOPING REQUEST OF
RKSCPL
Dear Sir,
This has reference to your meeting with ... de-scoping (of piling jobs/civil jobs / structural
steel jobs) from the said contracts provided that such de-
scoping is done by IOCL without
till June 30,
2017. A major portion of the works were de-scoped, vide agreement
dated May 11, 2018 as the respondent was unable ... delay caused by the respondent, and the
subsequent de-scoping, the petitioner incurred additional expenses.
The respondent also failed to adhere by the quality
your poor performance, SAIL
BSL had taken the decision of de-scoping your portion of the work
assigned under the contract and complete the same ... abundantly
clarify there is no prohibition on SAIL in de-scoping the work
originally assigned under your contractual obligations and/or
subsequent floating of tender
place. Finally, the six laning of
Dhanua portion had to be de-scoped from the contract owing to
delay in obtaining forest and wildlife clearance ... should have taken prudent action and would have advised NHAI
for de-scoping of the forest affected stretch to avoid prolongation
cost such as idling