your poor performance, SAIL
BSL had taken the decision of de-scoping your portion of the work
assigned under the contract and complete the same ... abundantly
clarify there is no prohibition on SAIL in de-scoping the work
originally assigned under your contractual obligations and/or
subsequent floating of tender
scope of work without amending the schedule of
rates.
21. It is submitted that the project as awarded to the plaintiff was de-
scoped ... de-scoped project was given at the risk and expense of the
plaintiff to another third party entity.
22. It is submitted that despite urgency
present, learned counsel for writ petitioners de-scopes the prayer in the
Page 4 of 9
WP and he submits that it would suffice ... hearing, more particularly owing to learned counsel for writ petitioners de-
scoping the prayer, we deem it appropriate to make a simple order directing
respondent
without prejudice to Prayer (d) above,
direct the Respondents to de-scope the residual works
(approximately 3-4%) from the original contractual scope under
Article ... Completion
Certificate and release all outstanding payments inclusive of the
de-scoped works to the Petitioner;
h) Issue a Writ of Mandamus or any other
scoped from the work of the concessionaire
of the Project.
10. That it has also been informed by the
NHAI that balance/de scoped work ... Certain works relating to
drain and service road etc. have been de scoped from the work
of the concessionaire of the project
consideration raised
by the respondent No.3-NHAI is regarding de-
notification/de-scoping of a portion of the acquired land,
record available
consideration raised
by the respondent No.3-NHAI is regarding de-
notification/de-scoping of a portion of the acquired land,
record available
consideration raised
by the respondent No.3-NHAI is regarding de-
notification/de-scoping of a portion of the acquired land,
record available
date of this Order. For hindered items, the
Claimant shall pursue de-scoping applications with the Respondent.
(g) Non-compliance of any one or more
concerned authority. However, stretch of 4.5 Km
has been de-scoped and is being dealt separately
with a separate agreement between NHAI and
EPC Contractor