Nabha Power Limited vs Punjab State Power Corporation Ltd & ... on 23 April, 2014
project implementation stage due
to change in the position of the Dedicated Freight
Corridor of the Railway one major bridge has to be
constructed ... another major bridge
has to be constructed to pass through the Dedicated
Freight Corridor lines. The Appellants claimed
additional capital cost of rail siding infrastructure