SCCL by University college of Engineering, Kakatiya University, Kothagudem
4. DGMS Permissions, SCCL Research & development wing study
5. Analysis report of Online monitoring ... conditions stipulated in the Environment Clearance,
Consent for Operation and other statutory DGMS permissions
obtained from time to time in both
report 7-9
C Proceedings before Tribunal 9-10
D Reply by DGMS, R-7 10-11
E Status of mine as per report ... DGMS 11-18
F Reply by Respondents 18-19
G Discussions 19-23
H Facts of O.A No. 75/2020 23-37
I Issues
Choudhary, Adv.
COUNSELS FOR RESPONDENT(S):
Mr. Om Shankar Shrivastava, Adv. for DGMS
Mr. Shubham Soni, Adv. for R-5
Mr. Rohit Sharma ... 2010 - Valid
ii. Consent condition - Issued.
iii. The NOC from DGMS Permission - Issued
13. The penalty has been imposed by the Mining Department during
Choudhary, Adv.
COUNSELS FOR RESPONDENT(S):
Mr. Om Shankar Shrivastava, Adv. for DGMS
Mr. Shubham Soni, Adv. for R-5
Mr. Rohit Sharma ... 2010 - Valid
ii. Consent condition - Issued.
iii. The NOC from DGMS Permission - Issued
13. The penalty has been imposed by the Mining Department during
Choudhary, Adv.
COUNSELS FOR RESPONDENT(S):
Mr. Om Shankar Shrivastava, Adv. for DGMS
Mr. Shubham Soni, Adv. for R-5
Mr. Rohit Sharma ... 2010 - Valid
ii. Consent condition - Issued.
iii. The NOC from DGMS Permission - Issued
13. The penalty has been imposed by the Mining Department during
Choudhary, Adv.
COUNSELS FOR RESPONDENT(S):
Mr. Om Shankar Shrivastava, Adv. for DGMS
Mr. Shubham Soni, Adv. for R-5
Mr. Rohit Sharma ... 2010 - Valid
ii. Consent condition - Issued.
iii. The NOC from DGMS Permission - Issued
13. The penalty has been imposed by the Mining Department during
Choudhary, Adv.
COUNSELS FOR RESPONDENT(S):
Mr. Om Shankar Shrivastava, Adv. for DGMS
Mr. Shubham Soni, Adv. for R-5
Mr. Rohit Sharma ... 2010 - Valid
ii. Consent condition - Issued.
iii. The NOC from DGMS Permission - Issued
13. The penalty has been imposed by the Mining Department during
Choudhary, Adv.
COUNSELS FOR RESPONDENT(S):
Mr. Om Shankar Shrivastava, Adv. for DGMS
Mr. Shubham Soni, Adv. for R-5
Mr. Rohit Sharma ... 2010 - Valid
ii. Consent condition - Issued.
iii. The NOC from DGMS Permission - Issued
13. The penalty has been imposed by the Mining Department during
Choudhary, Adv.
COUNSELS FOR RESPONDENT(S):
Mr. Om Shankar Shrivastava, Adv. for DGMS
Mr. Shubham Soni, Adv. for R-5
Mr. Rohit Sharma ... 2010 - Valid
ii. Consent condition - Issued.
iii. The NOC from DGMS Permission - Issued
13. The penalty has been imposed by the Mining Department during
Choudhary, Adv.
COUNSELS FOR RESPONDENT(S):
Mr. Om Shankar Shrivastava, Adv. for DGMS
Mr. Shubham Soni, Adv. for R-5
Mr. Rohit Sharma ... 2010 - Valid
ii. Consent condition - Issued.
iii. The NOC from DGMS Permission - Issued
13. The penalty has been imposed by the Mining Department during