dated 14th September, 2006. This is
also known as EIA Notification, 2006 (for short 'the Notification of
2006'). The Notification ... SEAC') takes the decision whether
Environmental Impact Assessment (for short 'EIA') Report has to
be prepared for the proposed projects. Stage
respondent. The Environment Impact
Assessment (for short 'EIA') submitted by the 4th respondent is inadequate, incorrect,
misleading and it is a fraud perpetrated ... respondent. The EIA has not been
prepared by an accredited agency. The public hearing conducted for the purpose of
the setting up the airport
EIA1994 60-67 42-47
EIA 2006 68-121 47-164
SSMG-2016 122-127 164-175
EMGSM-2020 128-134 175-185
Issue ... before the J&K
UT level EAC for appraisal under the EIA Notification, 2006. The
J&K UT level EAC in its 87th
that while transferring the EC the provision under Clause XI of the
EIA Notification 2006 were not followed.
A. Brief facts:
Case ... solely for the purposes of
considering the environment clearance as per the EIA notification issued
by Ministry of Environment, Forest and Climate Change. After
commencement of the
Pench diversion project without prior environmental clearance under the EIA
notification, 2006, was totally illegal and also for a direction ... hence, it is a major irrigation project listed in
Schedule of both EIA notification 1994 and 2006. Thus, requiring prior
environmental clearance from the Central
Solid Waste Management (for short "MSWM")
Project, Bareilly, under the EIA Notification of 2006 (for short the
'Notification'). Vide its letter ... prayed that since
the project in question requires EC under the EIA
Notification of 2006, no activity should be permitted to
be carried
Infrastructure on 25.4.2011. They further allege that the
project is covered by EIA Notification dated 27th January,
1994, read with EIA Notification dated ... that the present
Redevelopment Project of residential colony is covered by the
EIA Notification dated 27.01.1994 read with amended EIA
Notification dated
Environmental Clearance Regulations dated
14th September, 2006 (for short the "EIA Notification"). The
total land required for Stage-I was stated ... completely frustrated the advantages
of the public hearing, as contemplated under the EIA
Notification.
(iii) Various terms of the TOR have not been adhered
orders of the
21
2nd respondent. The Environmental Impact Assessment (for short, EIA) Notification dated
14th September 2006 of the Ministry of Environment and Forests ... issue appropriate guidelines from time to time as per the EIA Notification, 2006.
In the present cases, the SEIAA has sub divided projects
further submitted that the as per the EIA
Notification 2006 dated 14.09.2006, it is mandatory on the part of the
Project Proponent (PP) to obtain ... thereafter would seek Environment Clearance, ex-post
facto, making the provisions of EIA Notification infructuous, which would
defeat the very purpose of Environmental Protection