Fora, whereas
he should have filed an appeal
under Section 127 of the Electricity
Act, 2003. Having abandoned the
route for seeking relief under Consumer ... against the order of
Ombudsman nor exercise power under Section 127 of the Electricity Act,2003
The Honble National Commission further held that
since
then he should have preferred an appeal under
Section 127 of the said Electricity Act , but the District Forum is not the
proper forum ... therefore, the respondent should
have preferred an appeal under Section 127 of the Electricity Act against
the said assessment. The District Forum cannot hold that
liability regarding
payment of dues under the Electricity Act for the alleged act
of illegal consumption of electricity so far as the provisional
assessment stands ... Magistrate. However, the
petitioner may file an appeal under Section 127 of the
Electricity Act, 2003.
3) In the case of M/s. Classic
supply of electricity, cuts or injures, or attempts to cut or injure, any electric
supply line or works, shall be punishable with fine which ... Act, 2003 is maintainable before the Appellate Authority
under Section 127 of the Electricity Act, 2003.
8. Now we have to see whether the case
complainant and electric connection was severed and the meter and apparatus were taken away alleging that complainant has committed theft of the electricity. Complainant ... exhausted his remedies available under section 126 and 127 of Electricity Act of 2003. Therefore the complaint is to be dismissed.
4. The complainant
chose not to
prefer an appeal u/s 127 of the Electricity Act, the Complainant was statutorily
debarred from filing the complaint.
Ld. Forum below ... written protest from the Complainant/Appellant
,though under Section 127 of the Electricity
Act the Complainant could have gone for appeal . Acceptance of the final
liberty to
approach the appropriate authority as per The Electricity Act, 2003 .
8. The period spent while pursuing the complaint before the
District Forum ... which is required to be deposited as
per Section 127 (2) of the Electricity Act, 2003 for preferring the
appeal against the demand made under
liberty to
approach the appropriate authority as per The Electricity Act, 2003 .
8. The period spent while pursuing the complaint before the
District Forum ... which is required to be deposited as
per Section 127 (2) of the Electricity Act, 2003 for preferring the
appeal against the demand made under
liberty to
approach the appropriate authority as per The Electricity Act, 2003 .
First Appeal No. 1312 of 2007 3
8. The period spent while pursuing ... which is required to be deposited as
per Section 127 (2) of the Electricity Act, 2003 for preferring the
appeal against the demand made under
liberty to
approach the appropriate authority as per The Electricity Act, 2003 .
8. The period spent while pursuing the complaint before the
District Forum ... Section 127 (2) of the Electricity Act, 2003 for preferring the
appeal against the demand made under Section 126 of the Electricity
Act, 2003 before