value of flats, that the builder admittedly abandoned part of the said project. Flat purchasers in this complaint are similarly situated ... been paid in time, flats would have been completed in time. General slump in the market and seeing some flat purchasers getting their money back
garage" must be considered as would be understood by a flat purchaser and such person would contemplate garage which has a roof and wall ... open/stilt parking space as part of `common areas', every flat purchaser will have to bear3 proportionate cost for the same although
Jalandhar Improvement Trust & Anr. vs Rajinder Kumar Godara on 28 August, 2020
NATIONAL CONSUMER
Order dated 23.10.2018 allowed the Consumer Complaint filed by the Respondent - Flat Purchaser, and held that since the last date stipulated for construction had expired ... this period, the Respondent - Flat Purchaser had to service a loan that he had obtained for purchasing the flat, by paying Interest
cost
thereof in proportion to the carpet area of the flat from each flat purchaser.
Such stilt parking space being neither flat under Section ... were indulging in malpractices in the sale and
transfer of flats and the flat purchasers were being exploited. The effect of
MOFA may be summarized
Order dated 23.10.2018 allowed the Consumer Complaint filed by the Respondent - Flat Purchaser, and held that since the last date stipulated for construction had expired ... this period, the Respondent - Flat Purchaser had to service a loan that he had obtained for purchasing the flat, by paying Interest
Construction
could not be completed and booked flat was not available to the flat- purchaser
therein for a period of 11 years. In the
meantime ... towards the flat value.
On possession not being delivered, the flat-purchaser therein filed a
consumer complaint. The District Forum allowed the complaint partly, with
Order dated 23.10.2018 allowed the Consumer Complaint filed by the Respondent - Flat Purchaser, and held that since the last date stipulated for construction had expired ... this period, the Respondent - Flat Purchaser had to service a loan that he had obtained for purchasing the flat, by paying Interest
Order dated 23.10.2018 allowed the Consumer Complaint filed by the Respondent - Flat Purchaser, and held that since the last date stipulated for construction had expired ... this period, the Respondent - Flat Purchaser had to service a loan that he had obtained for purchasing the flat, by paying Interest
fact that a Public Notice dated 24.1.1999 was
given by the flat purchasers warning ... public at large not to deal with the
said flats. The flat purchasers had also
issued a letter dated 20.2.1999 to the builder