extension of time : No claim for compensation on account of delays or hindrances to the work from any cause whatever shall lie, except, as hereinafter ... contractor. The Executive Engineer shall assess the period of delay or hindrance caused by any written instructions issued by him, at twentyfive per cent
extension of time :--No claims for compensation on account of delays or hindrances to the work from any cause whatever shall lie, except as hereinafter ... Contractor. The Executive Engineer shall assess the period of delay or hindrance caused by any written instructions issued by him, at twenty five per cent
provides that no claim for compensation on account of the delays or hindrances to the work from any cause whatever shall lie except as mentioned ... precluded from claiming any compensation on account of the delays or hindrances arising from any clause whatever including those arising on account of acts
APDSS enjoins that no claim for compensation on account of delays or hindrances to the work from any cause whatever shall lie. The only remedy ... extension of time: No claim for compensation on account of delays or hindrances to the work from any cause whatever shall lie, except, as hereinafter
work, the claim of compensation on account of such delay or hindrance to the work is barred under ... submission that since any claim on account of such delay or any hindrance to the work for any cause whatever is not eligible
granted compensation on account of delays or hindrances to the work, that the arbitrator ought not to have allowed the market rate ... claim of the contractor for compensation on account of such delay or hindrance to the execution of the work is barred under
provides that no claim for compensation on account of the delays or hindrances to the work from any cause whatever shall lie except as mentioned ... precluded from claiming any compensation on account of the delays or hindrances arising from any cause whatever including those arising on account of acts
extension of time; No claim of compensation on account of delays or hindrances to the work from any cause whatever shall the, except, as hereinafter ... contractor. The Executive Engineer shall assess the period of delay or hindrance caused by any written instructions issued by him, at twenty five per cent
compensatory
afforestation. No claim for compensation on account of delays or
hindrances from whatsoever cause shall lie, but reasonable extension of
time will be allowed ... possible to conduct investigation for
which forest clearance was not a hindrance and in spite of the same the
first petitioner has not made
State Bank Of India vs Ram Das And Others on 12 March, 1998
Equivalent citations