Ashok Chhibber vs Hpgcl Through Managing Director ... on 24 January, 2019
Author: Ritu Bahri
Bench: Ritu Bahri
IN THE HIGH COURT OF PUNJAB AND HARYANA
Abhishek Goel vs Hpgcl on 19 July, 2019
Author: Harsimran Singh Sethi
Bench: Harsimran Singh Sethi
CWP-18394 of 2014 -1-
IN THE HIGH COURT
Hpgcl And Another vs Sohan Singh And Others on 4 April, 2019
Bench: Krishna Murari , Arun Palli
IN THE HIGH COURT OF PUNJAB AND HARYANA ... DATE OF DECISION: 04.04.2019
HPGCL and another
.....Appellants
versus
Sohan Singh and others
.....Respondents
CORAM:- HON'BLE MR. JUSTICE KRISHNA MURARI, CHIEF JUSTICE
during the relevant period to the Haryana Power
Generation Corporation Ltd (the HPGCL), he referred to the analysis and
conclusion of the Arbitral Tribunal that ... earlier obligation for the return of banked power that was supplied by
HPGCL to the first Respondent under a swap agreement. Consequently, he
contended that
issue of income from deemed generation, the same arises
when HPGCL does not take power from the power plant of the assessee. In
such ... that effect in the agreement
entered into between the assessee and HPGCL. There is no dispute about
these facts also. Thus, the only question left
fourth Respondent -- Haryana Power
Generation Corporation Ltd. (hereinafter referred to as 'HPGCL') on
01.03.2007 requesting for supply of 2000 MW power on long ... sell up to 500 MW power from the Project to HPGCL
and to take all necessary steps in this regard including submission of
bid, signing
under:-
1. Evaporation of surface moisture
2. Windage losses during transportation
HPGCL has coal based Thermal Power Stations located in State of Haryana for
generation ... generation of electricity.
The major content of Raw Material is Coal. HPGCL is purchasing coal through the
subsidiaries of Coal India Ltd. Coal India
Haryana Power Generation Corporation Ltd.
Urja Bhawan, C-7, Sector 6,
HPGCL, Panchkula 134 009,
Haryana (through its Managing Director)
Page 1 of 36
Order ... generator
(Lanco) on the one hand and retail supplier/distributor
(HPPC/HPGCL) on the other. In such circumstances, the
computation of energy charges carried
paid because there
was difference in quantity as recorded by DHBVN and HPGCL from the total
purchase 2227 crores. The reconciliation error amounts to only
Narender Hooda, learned counsel for the
DHBVNL, HPGCL and HVPNL has pointed out that
the expression ‗reservation' has to be interpreted by
referring