Resettlement Policies
framed by Haryana Urban Development Authority (for short 'the HUDA')
and/or by the State Government from time to time ... Mathias Oram (2010) 11 SCC 269 and Brij Mohan v. HUDA (2011)
2 SCC 29.) The fundamental right of the farmer to cultivation
that point.
HEADNOTE:
The State of Haryana through Haryana Urban Development
Authority (HUDA) acquired some land under the land
Acquisition Act for the purpose ... this matter by Haryana
State Industrial Development Corporation (HSIDC) which
showed that HUDA sold the land to HSIDC at a very high price
paid
Officer, Hyderabad Urban Development Authority, hereinafter referred to, for short, as "HUDA"; in other words, fixing the market value of the land acquired ... enhancement granted by the learned Subordinate Judge, the Land Acquisition Officer, HUDA preferred A.S.No. 2087 of 1991. Claimant has also preferred
that the suit premises have been constructed by Haryana Urban Development Authority (HUDA, for short), governed by the provisions of The Haryana Urban Development Authority ... short). The premises have been allotted by HUDA to the plaintiff-respondent and the latter is required to pay certain instalments to HUDA
lakhs shall be paid within 6
months of release of tentative layout
HUDA.
2. The sale shall take effect within 6 months
from the release ... period will be 8 MONTHS after
the release of TENTATIVE LAYOUT from
HUDA for SURVEY No. 36 of SATMRAI
Village and for SURVEY NUMBERS
acquired for Urban Mini Estate by the Haryana
Urban Development Authority (HUDA) and, for the said public
purpose, notification under Section 4 of the Land ... writ petitions, it transpires that
during their pendency, Chief Administrator, HUDA-cum-
Director, Urban Estates stated before the Division Bench on
January 8, 1998 that
presided over by the Administrator, Haryana Urban Development
Authority (for short ‘HUDA’). Reserve price had been approved by Chief
Administrator, HUDA. Though the reserved price ... issued inspite of efforts made by the
plaintiff. Officials of HUDA were dragging their feet over the issue
without any rhyme or reason.
Plaintiff ultimately
possession of land and handed-
over it to the Estate Officer, HUDA, Rohtak on that very day, i.e., 06th
April, 2005. The official record ... crop was standing could not be taken over by the
Estate Officer, HUDA, Rohtak/Land Acquisition Collector, Hissar as the land
owners were granted time
exchange deed (Annexure P-4) was
executed between Haryana Urban Development Authority (HUDA)
and respondents No. 5 and 6, namely, M/s NCR Residency ... recitals in the exchange deed, the first party (HUDA) is in
the process of developing a green belt on National Highway No. 10
bye-pass
even sanctioned the
water-connections to the plaintiffs. Defendant No.1-HUDA was stated to be
acting in collusion with defendants ... actual backdrop that the suit had been instituted.
6. Defendant No.1-HUDA filed a written statement stating therein
that the land in question along